Lord Bradshaw
Main Page: Lord Bradshaw (Liberal Democrat - Life peer)Department Debates - View all Lord Bradshaw's debates with the Department for Transport
(12 years, 11 months ago)
Lords Chamber
To ask Her Majesty’s Government, following the recent award to Bombardier of the contract for 130 new carriages, what further plans they have for maintaining train design or manufacturing capacity in the United Kingdom.
My Lords, we believe that in most cases the procurement of rolling stock should be led by the rail industry, but in cases where the Government are involved we will take on board the conclusions of the Government’s recent review of procurement to give suppliers confidence to invest in their capability to meet future demand by publishing pipelines of future government needs and taking action to remove barriers to growth.
The announcement of the new train order to Bombardier took place 1,000 days after the last order was placed. There is no doubt that the Government are deeply involved because the short term of franchises means that no rolling stock company can get its money back in the duration of the franchise. The Answer that I have been given is quite disingenuous. I really want some assurance that British industry will be supported. It has only 100 days work from this new order and it is time that something was done to extend that period.
My Lords, noble Lords will know that this Government have made considerable investment in the rail industry and will continue to do so. Noble Lords should also be aware that there is considerable refurbishment work available on the existing rolling stock in order to make it compliant with new accessibility requirements.