Procurement Bill [ Lords ] (Fourth sitting) Debate
Full Debate: Read Full DebateFlorence Eshalomi
Main Page: Florence Eshalomi (Labour (Co-op) - Vauxhall and Camberwell Green)Department Debates - View all Florence Eshalomi's debates with the Cabinet Office
(1 year, 10 months ago)
Public Bill CommitteesThe clause explains what we mean by “award criteria”. They are the criteria against which contracting authorities assess tenders under a competitive tendering procedure, and the clause sets out the rules that apply to them.
The clause requires that award criteria are clear, measurable and specific, comply with the rules on technical specifications, are a proportionate means of assessing tenders, and relate to the subject of the procurement. The clause requires that the way in which tenders are evaluated is transparent and set out in the assessment methodology, and that contracting authorities set out the relative importance of the criteria.
The clause makes it clear that award criteria can cover a wide range of things, from price to how things are produced to what happens at the end of the solution’s lifecycle, provided criteria relate to the subject matter of the contract. The rules allow a contracting authority to limit the number of lots that it wishes to award to a single supplier, when it has broken down a larger procurement into smaller lots or components. Where the contract is for light-touch services, which are person-centred services, reference is made to additional matters that can be considered to be relevant to the subject matter of the contract.
We want contracting authorities to be confident when designing and running procurement procedures. An area that often causes confusion is how far award criteria can be iterated during the process. Given the flexibility afforded to contracting authorities under the new regime, clause 24 makes it clear that award criteria may be added to through greater detail, or tweaked to add clarity during a procurement procedure, but any such refinements to award criteria should be made at specified points. The clause does not allow for wholesale changes to award criteria. For example, during a procurement procedure that allows for a research phase, a design phase and a development phase, the overarching criteria will remain constant, but the specifics may evolve. That is what the clause seeks to achieve.
It is a pleasure to serve under your chairship, Mr Mundell.
Clauses 23 and 24, as the Minister highlighted, relate to the award criteria and their refinement before the invitation of tenders. Award criteria for procurement need to be finely balanced to achieve the best deal for the public. If they are too narrow, we risk missing out on innovative processes, and the potential to save the taxpayer money and deliver those services efficiently; if they are too broad, we risk delivering substandard and inappropriate services.
In the lead-up to our consideration of the Bill, I spoke to different groups and charities. They said that broad contract terms often mean that contracting authorities end up awarding the contract to the cheapest bidder. That is despite the charities offering more bespoke and important services that address the needs of procurement far more substantially.
The clause sets out a specific and somewhat technical provision, whereby a contracting authority can either permit or direct a supplier to subcontract the supply of goods, services or works to another supplier.
In certain procurements, circumstances exist where part of the contract needs to be subcontracted to a specified supplier. That could be due to economic or technical reasons relating to requirements of interchangeability or interoperability with existing equipment, services or installations. It could also be due to the protection of exclusive rights.
For example, a contracting authority might require the use of certain technical software that is owned by a single supplier. Therefore, in such procurements, a contracting authority may need to nominate a particular subcontractor that must be used. For direct award under clause 41, however, a contracting authority may only require a supplier to subcontract the supply of goods, works or services to a particular supplier where the justifications for a direct award set out in schedule 5 also apply to the subcontractor.
The clause states that where a contract could be supplied to a supplier under a direct award, the contracting authority can mandate that a supplier that wins a competitive tender process must subcontract the supply of those works, goods and services to the supplier that could have supplied the contract via a direct award. We have discussed the issues of subcontracting and of direct awards, and we will discuss them further under clauses 71 and 41 respectively. This clause is relatively uncontroversial, in that it seeks to ensure that the mechanisms for direct awards can apply via a subcontract. We therefore do not wish to oppose the clause and are happy for it to stand part of the Bill.
Question put and agreed to.
Clause 25 accordingly ordered to stand part of the Bill.
Clause 26
Excluding suppliers from a competitive award
Question proposed, That the clause stand part of the Bill.
We come to the clauses concerning the exclusion of suppliers. I appreciate that there is considerable interest in these clauses, and rightly so; they are an important part of the Bill.
Clause 26 sets out the basic principles governing the exclusion of suppliers from competitive award of contracts. Subsection (1) provides that contracting authorities must disregard tenders from suppliers that are “excluded”. Excluded suppliers are defined in clause 57 as those in respect of which a mandatory ground for exclusion applies, as set out in schedule 6, and the issues in question are likely to occur again, or that are otherwise treated as excluded suppliers under the Bill.
Subsection (2) provides that contracting authorities must consider whether a supplier is an “excludable supplier” before assessing tenders, and may, at their discretion, disregard tenders from such suppliers. Excludable suppliers are those in respect of which a discretionary exclusion ground applies, as set out in schedule 7, and the issues in question are likely to occur again.
Subsection (3) requires contracting authorities to give the supplier the opportunity to replace an associated person, such as a subcontractor that the supplier is relying on, to meet any conditions of participation, if the exclusion situation pertains to such a supplier.
Clause 26 is essential to give effect to the exclusions regime set out in the Bill with regard to the assessment of tenders, which protects contracting authorities and the public from suppliers that may not be fit to compete for public contracts. However, the clause does not provide the detailed grounds for exclusion and the process for how authorities should apply them. Those are set out in clause 57 and in schedules 6 and 7, which we will come to on a future day.
Clause 27 sets out the basic principles governing the exclusion of suppliers from competitive, multi-staged procurements. Those provisions are needed in addition to clause 26 to ensure that contracting authorities consider the exclusions at the start of multi-stage procedures, as well as when considering tenders.
Subsection (1) provides that contracting authorities must apply the exclusions regime to interested parties at the outset of all multi-staged procurements. For those procurements, authorities should consider whether each interested supplier meets any of the grounds for exclusion and, if so, whether the issues in question are likely to occur again, and whether that supplier is to be treated as an excluded supplier under the Bill for other reasons.
If a supplier is an excluded supplier under subsection (2), the authority must prevent the supplier from participating in, or advancing any further in, the procurement. Where the supplier is an excludable supplier under subsection (3), the authority may, at its discretion, permit the supplier to participate. That has the effect of making exclusions a gateway into the procurement.
Subsection (4) requires contracting authorities to give the supplier the opportunity to replace an “associated person”, such as a subcontractor the supplier is relying on, to meet any conditions of participation, if the exclusion situation pertains to such a supplier.
Clause 27 is essential because it gives effect to the supplier exclusion regime set out in the Bill, which protects contracting authorities and the public from suppliers that may not be fit to compete for public contracts. However, as with clause 26, clause 27 does not provide the detailed grounds for exclusion and the process for how authorities should apply them. Those are set out in clause 57 and schedules 6 and 7.
Clause 28 deals with exclusions and subcontractors. It sets out the circumstances in which contracting authorities must, or may, consider whether the exclusion grounds apply to subcontractors that the bidder in question intends to work with, and how to apply the exclusion regimes where that is the case. Importantly, that is not limited to direct subcontractors of the bidder but includes other subcontractors further down the supply chain.
Subsection (1) requires contracting authorities to request information from suppliers about all intended subcontractors and to check that they are not on the debarment list. Subsection (2) then allows contracting authorities to request additional information about any subcontractors and consider whether they are excluded or excludable suppliers. Contracting authorities may choose to do that for particular types or categories of subcontractors, such as all first-tier subcontractors or service-critical subcontractors.
If a subcontractor is an excluded supplier under subsection (3), the contracting authority must disregard their tender and exclude them from taking part in a competitive tendering procedure. If the subcontractor is an excludable supplier under subsection (4), the contracting authority may disregard their tender or exclude them from the procedure. Before disregarding a supplier’s tender or excluding them from a procedure under this clause, under subsection (5), the contracting authority must give the supplier the opportunity to replace the subcontractor in the supply chain in order to avoid itself being excluded.
We know that some of the worst corporate misconduct and unlawful behaviour occurs deep in supply chains to Government. That is particularly true with respect to forced labour and other modern slavery abuses. This clause is essential to ensure that the same standards to which we hold bidders for contracts can be applied all the way down the supply chain.
Clauses 26 to 28 concern the exclusion of suppliers on the grounds listed in schedules 6 and 7 related to mandatory and discretionary grounds for exclusion. We support the inclusion of exclusion grounds in the Bill. In the Green Paper “Transforming Public Procurement”, the Government said:
“The current procurement regulations allow contracting authorities to take into account the past performance of a supplier on only very limited grounds and commercial teams often have to rely on bidders’ self-declarations rather than objective, evidence-based information. We can act now to raise the bar on the standards expected of all suppliers to the public sector and ensure that outstanding small suppliers are able to secure more market share, increasing productivity and boosting economic growth.”
I am sure that there is complete agreement on that in the Committee today. There can be no question but that we should not give public money to those convicted of wrongdoing or acting in a way that damages the country and our communities.
Clauses 26 to 28 put into place terms to bring the mandatory exclusion grounds from schedule 6 and schedule 7 into force by using the language of “excluded” and “excludable”, as defined in clause 57. Of course, the strength of this clause is heavily determined by the strength of the grounds for exclusion.
We are pleased to see some steps forward from the system inherited from European Union directives, which was brought into power in this country via the Public Contracts Regulations 2015. In particular, we are pleased to see environmental misconduct implemented as a discretionary exclusion ground. Our environment is a key natural asset that provides us with the building blocks for living in this country. Those who seek to damage our environment—for example, by dumping waste and causing significant damage to plant or animal life—should not be given Government contracts. We are also pleased to see national security within the system, although, as the Minister can guess from our planned amendments, we feel that this could have a stronger presence in the Bill, with some of the ambiguity removed.
When reading through the clause, we had some concerns about how it will be applied and some of the doors that it leaves open on discretionary exclusion grounds. Although the Bill is clear that those excluded on mandatory grounds must be disregarded from a tendering process, it is not clear on the fate of suppliers that fall foul of the discretionary grounds. Here, the Bill says that contracting authorities “must consider” whether a supplier is excludable on discretionary grounds but “may disregard” their tender, as the Minister said. This discussion may seem similar to ones we have already had, but this could have far more serious consequences.
For example, let us say that a supplier is decided to be a national security risk following an assessment by a contracting authority and that is confirmed by the Government via the provisions in clause 29. That supplier then applies for a tender to another contracting authority. What is stopping that contracting authority awarding this contract, should it so wish? There does not seem to be any mechanism to permanently exclude an excludable supplier in the Bill. Even when the Government consider a threat so severe that it should go on the debarment list, the Bill would still allow authorities to apply the “may” rather than the “must” exclude part.
I am sure the Minister will say that he will issue clear guidance on this and that contracting authorities should, of course, exclude a supplier in this case, but these are serious grounds for exclusion; we all agree on that. We cannot leave it to chance that a contracting authority uses the powers as they are written in the Bill, rather than as the Minister wishes. At the very least, that creates ambiguity around the whole system.
On that final point, the hon. Lady will have heard me say that we intend to introduce a major programme of training and guidance across many areas covered by the Bill, as part of breathing new life into procurement in our country.
On the hon. Lady’s previous points, this part of the Bill deals with the creation of the mechanism, the details of which are dealt with subsequently in the Bill. The mechanism is that there are some discretionary grounds for exclusion and some mandatory grounds for exclusion. When we get to the relevant clauses and schedules, we will be able to put our arguments, and she and her party can say whether they think that certain issues should be mandatory or exclusionary. I think she will see, when we get there, that sometimes there are grounds for mandatory exclusion on particular issues, but sometimes, on a different version of the same issues, there can be grounds for discretionary exclusion. As I say, we will get into the detail of that as we progress.
Question put and agreed to.
Clause 26 accordingly ordered to stand part of the Bill.
Clauses 27 and 28 ordered to stand part of the Bill.
Clause 29
Excluding a supplier that is a threat to national security
I beg to move amendment 18, in clause 29, page 20, line 42, leave out
“paragraph 14 of Schedule 7”
and insert
“paragraph 42A of Schedule 6”.
This amendment is consequential on Amendment 15.
With this it will be convenient to discuss the following:
Amendment 15, in schedule 6, page 104, line 25, at end insert—
“National security
42A A mandatory exclusion ground applies to a supplier if a decision-maker determines that the supplier or a connected person poses a threat to the national security of the United Kingdom.”.
This amendment, together with Amendment 16, would move national security from among the discretionary exclusion grounds in Schedule 7 to the mandatory exclusion grounds in Schedule 6.
Amendment 16, in schedule 7, page 110, leave out lines 28 to 31.
See explanatory statement to Amendment 15.
Amendment 17, in schedule 7, page 111, line 39, leave out sub-sub-paragraph (e).
See explanatory statement to Amendment 15.
Amendment 19, in clause 78, page 53, line 38, leave out
“paragraph 14 of Schedule 7”
and insert
“paragraph 42A of Schedule 6”.
This amendment is consequential on Amendment 15.
New clause 1—National Security Procurement Committee—
“(1) The Secretary of State must establish a committee, chaired by the Minister for Resilience, to consider (a) national security and (b) cyber security within the Government’s supply chain.
(2) The committee must consider whether suppliers should be excluded on the basis of the discretionary exclusion ground in paragraph 14 of Schedule 7 (threat to national security).
(3) The committee must review ongoing major government contracts, with focus on threats to national and cyber security.
(4) The committee must meet no less than once every three months.”
This new clause will mandate that a new committee must be set up with a view to proactively identifying potential security threats within the Government’s supply chain.
New clause 4—Dependence on high-risk states—
“(1) The Secretary of State must within six months publish a plan to reduce the dependence of public bodies upon goods and services which originate in whole or in part in a country considered by the United Kingdom as a high risk sourcing country.
(2) For the purposes of this section, a country is considered a high risk sourcing country by the United Kingdom if it is defined as either a systemic competitor or a threat in the latest Integrated Review of Security, Defence, Development and Foreign Policy.”
Amendments 18 and 15 to 19 relate to the discussions that we just had—on clauses 26 to 29 stand part—on exclusion and excludable grounds. Taken together, the amendments would move the national security ground for exclusion from schedule 7 to schedule 6. In practice, that would mean taking the consideration that a supplier is a threat to national security from being a discretionary to a mandatory ground.
As I mentioned, we considered removing the distinction between mandatory and discretionary grounds entirely in the Bill, and to some degree, the amendment serves as the first step towards considering wider reform of these parts of the Bill. However, we believe there is a particular case for national security to be a mandatory, not a discretionary ground.
Perhaps the Minister can cast his mind back to Second Reading, over a month ago. During that debate, Members on both sides of the House raised a number of valid concerns about national security in procurement. We in the Opposition share those concerns. Procurement deals with our basic infrastructure and offers a million doors into our country to those who represent a security threat. We cannot be too arrogant to believe that those who represent such a security threat cannot think of innovative ways to get access to critical and sensitive information.
Just last month, we heard how SIM cards capable of tracking location were found in ministerial cars, which was very concerning. We need to think about all the data that could be revealed and the sensitive information that could end up in the hands of malign actors. Even for minor contracts, important information about the country could be extracted without our knowledge. It is worth reiterating that we cannot be too arrogant about knowing what information is sensitive and what is not.
As we enter the age of the internet, our data and the strength of our infrastructure become more valuable and at even greater risk. There is no room to open up the operating strands of the country to national security risks. Doing so confers unnecessary risk on the state.
Let me take the Minister’s mind back to the speech from his hon. Friend the hon. Member for Rutland and Melton (Alicia Kearns). He can look at some of the points she highlighted if he doubts the severity and importance of the issue. She made a powerful case, and the test for what constitutes a national security threat should be strong, as it is in the Bill.
Clause 29 provides that suppliers may be excluded on those grounds only with the express permission of a Minister. It is right to have that test in the Bill, as no one wants contracting authorities making decisions on such important matters. However, it makes no sense for there to be such a high-level test in the Bill if no high-level response comes with it. It also makes no logical sense to the path of decision making in the Bill. It also makes no logical sense for the path of decision making in the Bill. If the matter is so important that the decision to exclude cannot be left to authorities, why do contracting authorities have discretion to decide whether to disregard a tender? Surely at the very least the decision to disregard a tender should also be taken at Secretary of State level. Under the Bill, even when the Secretary of State decides to place a supplier that is deemed to be a national security threat on the debarment list, contracting authorities still have discretion over whether to award the contract.
It does not take much imagination to see that an under-resourced contracting authority might decide that national security issues were not relevant to a small contract, and that could inadvertently open a door to sensitive information being shared. We are clear that there are no circumstances where a national security threat should be awarded a Government contract.
There is an unacceptable and unknown threat associated with having suppliers that are considered a national threat in our procurement system. I welcome the positive Government amendments that go in the direction of acknowledging that; the Bill is a step forward on national security. However, amendments 15 to 19 are the only way to close the loopholes in our procurement system.
In the Select Committee, the hon. Member for Rutland and Melton said that
“we must ensure we do not end up in a relentless whack-a-mole trying to hunt down the companies responsible for such things. We need to focus on the components within sensitive industries or sensitive items, and to ensure that any public body procuring such components or companies within relevant industries must come to someone for a second review. That means we are not attacking a specific country and saying China’s products are bad or saying that certain companies are awful; we are doing due diligence in sensitive areas. That is why we need a SAGE-style committee on public procurement specifically looking at national security.”
We completely agree with that sentiment. New clause 1 is an attempt to bring to life that committee in the style of the Scientific Advisory Group for Emergencies. As I said on amendment 11 to clause 13, there are a multitude of examples from the past decade of procurement giving rise to national security concerns, the latest of them involving SIM cards being found in ministerial cars; I mentioned that earlier. We are seeing the same questions arise throughout our debates. What damage has already been done? How much will it cost to repair? How did we not spot this earlier? These are all good questions. Without fail, the answer to all those questions is that the cost and damage is far greater than if we had acted earlier and prevented concerns from arising.
I hope the Minister will agree that new clause 1 aims for a cultural change in national security and procurement. We cannot afford to be reactive when it comes to national security threats. The sooner we act, the less valuable information we lose, and the less risk we are at from the threats that we identify. The SAGE-style committee could consider whether a supplier could be excluded on national security grounds. It could also consider wider threats across the supply chain. In his closing remarks on amendment 11, the Minister said:
“National security is, of course, of paramount importance.”––[Official Report, Procurement Public Bill Committee, 31 January 2023; c. 63.]
That being so, I hope that he will support new clause 1.
Clause 29 adds provisions relating to exclusion on national security grounds; it ensures that the grounds for exclusion are verified by the Secretary of State. Declaring that a supplier is a threat to national security is serious, and it is right that there be scrutiny in the system to ensure that contracting authorities do not do it lightly, or without due care. I hope the Minister can inform me how that will interact with the debarment test that he mentioned. Given the scrutiny and certification that is needed if a supplier is to be disregarded on the grounds that they are a national security threat, it is logical that the great bulk of those suppliers will end up on the debarment list. Can the Minister confirm whether that is the case? If it is not, what circumstances relating to national security would lead to a supplier not being added to the debarment list?
Clause 30 requires contracting authorities to exclude suppliers that have gained an unavoidable, unfair advantage in a procurement as a result of improper behaviour in relation to that procurement, and suppliers that have failed to provide an accurate and complete list of connected persons and associated persons when requested to by the contracting authority.
Subsections (1) and (2) are clear that exclusion as a response to improper behaviour, defined in subsection (4), is a last resort. It is to be used only where the supplier has gained an unfair advantage that cannot be remedied other than by exclusion. Subsection (3) requires contracting authorities to give suppliers the opportunity to remedy their improper behaviour. When suppliers seek to tilt the playing field in their favour via mis-representation or undue influence, and fail to remedy that, it makes fair and open competition for contracts impossible, and it is taxpayers who pay the price.
Transparency is another essential component of fair procurement, so subsections (5) and (6) are clear that suppliers that are not prepared to disclose full and accurate details of their connected persons, including beneficial owners and directors, or associated persons—for example, subcontractors that are relied on to meet conditions for participation in the procurement—are not fit to bid for public contracts. Contracting authorities must know who owns or has control over the suppliers with which they are contracting. The clause will support them in gaining that knowledge.
As the Minister has highlighted, clause 30 concerns the exclusion of suppliers who behave improperly during the procurement process. It is important that we do not tolerate improper behaviour in procurement. Many procurement contracts are public-facing and require a huge amount of trust, because the suppliers represent the contracting authority to the public. If there is evidence of misleading and improper behaviour that betrays a lack of integrity during the procurement process, it will raise doubts about whether such behaviour may flow through into how the company carries out the contract. Critical goods are procured via these processes, which are vital to the way our country functions, and we cannot let those who embellish their evidence during the tendering process have access to our supply chains.
The Opposition support the clause, but I have a few questions about how it will work. What steps will be taken to establish improper behaviour during the tendering process? What steps can be taken if information comes to light after the award of a contract? It is crucial that improper influence does not permeate into our procurement system; the measures in the Bill can prevent that, but there also needs to be transparency in the system so that we can spot things like undue influence and prevent improper behaviour from falling through the cracks. What steps is the Minister taking to ensure that undue influence, both formal and informal, is spotted during the procurement process?
I must also ask what consistent remedy is available to contracting authorities that find out about breaches following the award of a contract. Let me take hon. Members back to the covid-19 scandal, when billions of pounds-worth of unsellable personal protective equipment was written off. I know that that was not all due to fraudulent behaviour from suppliers, and that some fraudulent behaviour would not fall under the clause if a competitive tender were used. However, it is shocking that the Government admitted on 20 December 2022, in answer to a parliamentary question, that only £18 million of taxpayers’ money had been clawed back from PPE contracts.
There needs to be stronger clawback and remedies when suppliers act improperly. Perhaps that is a matter of culture more than legislation, as many contracts include such a clause, but it would still be helpful to hear what the Minister thinks needs to be done to ensure that more public money is clawed back from those who act improperly.
In answer to the hon. Lady’s final point, the Government are absolutely seeking to recover public money. The Department of Health and Social Care has been in a process of mediation, but obviously there will come a point at which mediation may need to lead to litigation. Contracts have been drawn up in a way that ensures that we can do the right thing by taxpayers.
On the hon. Lady’s earlier point, I can reassure her that we will publish guidance to support contracting authorities in this area, so that they can conduct due diligence on suppliers and their connected persons.
Question put and agreed to.
Clause 30 accordingly ordered to stand part of the Bill.
Clause 31
Modifying a section 19 procurement
Question proposed, That the clause stand part of the Bill.
There will be times when changes need to be made to the terms of a procurement. Clause 31 sets the scope for such modifications, with the intention of striking a balance between permitting changes required by contracting authorities and preventing abuse of that flexibility, for example to suit a particular supplier. Modifications are allowed in all procedures, but—with the exception of light-touch contracts, which have greater flexibility—they must be confined to non-substantial changes. In essence, that prevents a change that would be likely to impact the market response to the procurement.
Where a permitted modification is made, the contracting authorities must, in consequence, consider revising the time given to suppliers to respond to the invitation to tender or request to participate. The making of modifications will also be transparent, as the contracting authority must provide revised documentation that highlights the changes.
Clause 31 relates to the modification of a section 19 procurement prior to the deadline for submitting a request to participate in the procedure, where there has been no invitation to submit such requests. This sensible clause has proportionate provisions relating to the alteration of contracts. It is right that contracting authorities should be able to modify terms early in the process and carry out later alterations where they are not substantial, or relate to light-touch contracts.
Amendments 32 and 33 seek to ensure that the provision is applied widely and as intended, so as to support disabled or disadvantaged people who might otherwise struggle to find employment effectively. Many of the organisations that wish to provide that assistance through the delivery of public contracts do so via arrangements commonly referred to as “employment programmes”, which can be established by one organisation or a number of organisations working together. We need to ensure that those programmes can qualify for a reserved contract. Amendments 32 and 33 therefore seek to clarify that the 30% threshold for disabled or disadvantaged workers can be applied to the programme or part of an organisation, and not just to the organisation as a whole. Where a programme is established as a result of organisations working together, each organisation can contribute to the 30% threshold.
The amendments also seek to clarify that, in order to qualify, an organisation does not necessarily need to have been set up with the sole purpose of assisting disabled or disadvantaged people in employment, but the part of the organisation interested in delivering the contract must have that purpose. This may be a subsidiary or a specific project within an organisation. Where it is applied to a programme made up of a number of organisations working together, the purpose applies to the programme.
Clause 32 allows procurements to be reserved for organisations that provide employment and/or assistance in finding and retaining employment for disabled or disadvantaged people, allowing public procurement to support organisations that assist people who might otherwise struggle to access the labour market, while delivering public services to a high standard. Such companies are often not for profit and will therefore benefit from a more level playing field when competing for a reserved procurement than might otherwise be the case. In order to qualify, the organisation, or an arrangement between organisations, must have the aim of assisting disabled or otherwise disadvantaged people in employment, and at least 30% of the workforce must be disabled or otherwise disadvantaged.
I thank the Minister for his explanation of amendments 32 and 33. We support the use of supported employers and believe that they could go even further, as I will argue in relation to our amendments 92 to 94, but I will first touch on amendments 32 and 33.
We are concerned that Government amendments 32 and 33 expand the definition of supported employment provider so that it would apply where the part of the organisation delivering the contract would meet the relevant thresholds, which could potentially allow for a further watering down of the requirements. Has the Minister considered the potential of the amendments to limit the effectiveness of supported employment by allowing more providers that are not focused on the needs of disabled people to access reserved contracts, or even the potential for larger contractors to game the system? We do not intend to push the amendments to a vote, but I would welcome clarity from the Government and I hope that the Minister’s response will satisfy me. We reserve our right on that.
On amendments 92 to 94, supported employment is a long-established practice and plays an important role in increasing employment opportunities for disabled people. The principle of reserving contracts so that only supported employment providers can bid for them is welcome. However, there are concerns that the Bill does not set a sufficiently high bar for an organisation to be a supported employer, dilutes the aims of reserving contracts and potentially opens the system to abuse.
The Public Contracts Regulations 2006 required 50% of employees to be disabled people, which provided a greater focus on the specific aim of supporting the employment of disabled people. Clause 32 instead enshrines the weaker standard defined in the Public Contracts Regulations 2015, which require only 30% of workers to be disabled or disadvantaged. That potentially limits the impact of supported employment in providing employment opportunities for disabled people.
Concerns have been raised that that approach does not fully recognise the importance of deaf and disabled people’s organisations, or DDPOs, which not only provide supported employment but have a wider role in society. There are clear links between the work of DDPOs and social value. DDPOs protect and uphold disabled people’s rights, campaign for equality and inclusion, and provide a range of peer-led accessible services. Their services support disabled people in accessing services and entitlements, challenging discrimination and exclusion, and having choice, control and independence.
Amendments 92 to 94 would return to the broad definition of a supported employment provider set out in the Public Contracts Regulations by requiring 50% of employees to be disabled and placing a greater emphasis on the role of DDPOs. Inclusion London, a membership body for DDPOs in London, defines a DDPO as an organisation the management committee or board of trustees of which has at least 75% representation from deaf and disabled people, the staff of which is made up of at least 50% deaf and disabled people at all levels of the organisation, and that works to provide services for or works on behalf of deaf and disabled people.
Amendments 92 and 93 would remove “disadvantaged” from the definition. Disability is clearly defined in the Equality Act 2010, which provides a more robust definition that would ensure that the aim of reserving contracts is effectively targeted at the right providers. Did the Government consider the merits of the 2006 definition in preparing the Bill, and did the Government assess whether that definition more effectively targeted the measure of reserving contracts? Will the Minister consider engaging with DDPOs to ensure that the benefits of those organisations are considered in implementing the Bill?
Clause 33 operates similarly to clause 32, but allows only specific procurements to be reserved for organisations that have spun out of the public sector to provide social services, with company decisions managed by company employees. Those companies are known as public service mutuals.
Public service mutuals play a vital role in supporting communities at a local level, delivering essential services and contributing to economic growth. However, they may struggle to compete with larger or more well-established suppliers, and it is therefore appropriate that we encourage these public service mutuals by enabling competition in certain limited circumstances among only those organisations that meet the requirements of this clause.
Subsection (6) provides a full definition of a public service mutual body for the purposes of applying this clause. For example, in order to qualify, the company must be run on a not-for-profit basis or restrict the distribution of profits to its members. The exact list of services that can be reserved under clause 33 will be provided in secondary legislation under subsection (8). All reservable services are also light-touch services; examples include adult educational services and rehabilitation services.
As the Minister has mentioned, clause 33 gives contract authorities the ability to reserve certain light-touch contracts for public service mutuals. I am pleased to discuss this matter; as a very proud Labour and Co-operative MP, I am happy to have another opportunity to talk about how fabulous co-operatives are and how they can benefit the public sector. It is fair to say that the Minister and I agree that public service mutuals have so much to offer in terms of innovation and how they can help the wider public sector. The running of services by people rooted in their community helps to bring an understanding of local needs to the heart of public service mutuals, and they can also improve both employee morale and the quality of services for users.
This substantial grouping of clauses is of considerable importance to the Bill.
Clause 34 relates to the awarding of contracts under the new concept of a dynamic market. This is a highly flexible commercial tool. Dynamic markets are established by contracting authorities and essentially are “live” lists of suppliers that are pre-qualified to deliver certain types of contracts.
Dynamic markets are similar to existing dynamic purchasing systems, in that they will allow for suppliers to be admitted to the market if they meet the conditions of membership. To maximise the benefits of this flexible purchasing tool, we have significantly broadened the type of contracts that can be awarded in dynamic markets. Dynamic markets will be available for all types of procurement and not just for commonly used goods and services, as was the case for dynamic purchasing systems.
Clause 34 is the first in a series of clauses relating to dynamic markets. It allows a contracting authority that has established a dynamic market to award contracts under the market by undertaking a competitive flexible procedure. The use of a dynamic market does not avoid the need to comply with the usual rules for a competitive flexible procedure under clause 20.
Subsection (1) allows contracting authorities to restrict procurements to suppliers that are members of a dynamic market or a part of the market, for example if the dynamic market comprises categories of works or services. A supplier will be a member of a dynamic market if the market allows for the award of the contract in question by that contracting authority and the supplier has been admitted to the market. Subsection (3) requires contracting authorities to disregard tenders from suppliers that are not members of the dynamic market.
Dynamic markets are open to new suppliers to join at any time, as long as they meet the conditions for membership, which is a substantial improvement on the way things have been done up to this point. For that reason, subsection (4) requires contracting authorities to consider membership applications from non-member suppliers before excluding them from the procedure or disregarding their tenders. Subsection (5) says that the only exception to that is where, due to the complexity of the procurement, the application for membership cannot be considered in the timescales set out by the contracting authority for requests to participate or tenders.
Clause 35 sets out how dynamic markets, including utilities dynamic markets, may be established. It allows contracting authorities to establish arrangements known as dynamic markets, which are essentially live lists of suppliers that are pre-qualified to deliver certain types of contracts for the purpose of contracting authorities awarding contracts to suppliers that are members of the dynamic market.
Subsection (2) defines a utilities dynamic market, which is a particular type of dynamic market for the award of utilities contracts by utilities. Subsection (3) allows utilities to award utilities contracts under a utilities dynamic market established by any person, as long as the market has been established in accordance with the rules applicable to utilities dynamic markets as established by private utilities.
Subsection (4) defines a utility as a public authority or public undertaking that carries out a utility activity or a private utility. Utility activities are set out in schedule 4; private utilities are defined in clause 2. Subsection (5) states that the establishment or modification of a dynamic market is not a contract for the purpose of the Bill, making it clear that all the rules on the award of contracts do not apply.
Clause 36 sets out the rules on how suppliers can become members of dynamic markets, including utilities dynamic markets. Subsection (1) allows contracting authorities to set conditions of membership that suppliers must meet in order to be admitted to a dynamic market. The conditions of membership must be a proportionate way of assessing suppliers’ legal and financial capacity and technical ability to deliver contracts that might be awarded as part of the arrangement.
Subsection (2) prohibits conditions of membership that require the submission of annual audited accounts by suppliers that are not already required by law to have their annual accounts audited. It also prohibits conditions of membership that require insurances to be in place before the contract is awarded. As hon. Members will be aware, this is a major boon to SMEs that are seeking to get involved.
The restrictions on the conditions of membership of a dynamic market, set out in subsection (3), are similar to those applicable to conditions of participation in a competitive tendering procedure under clause 22. They include limiting conditions to those that are a proportionate means of ensuring suppliers have the relevant qualifications, experience and technical ability to perform the contract, ensuring that the conditions do not break the rules on technical specifications, and requiring that equivalents must be allowed where particular qualifications are required.
Subsection (4) says that when deciding on what is proportionate, the contracting authority must have regard to the types, complexity and cost of contracts that will be awarded through the dynamic market. Subsection (5) ensures that contracting authorities can require evidence that a condition of membership is met to be independently verifiable by a person that is not the supplier.
Subsection (6) ensures that dynamic markets remain open to new suppliers as long as the dynamic market is in operation. Applications for membership must be considered within a reasonable period and suppliers must be informed of the outcome of their application, with reasons. Suppliers that meet the conditions of membership must be admitted to the market in a timely manner. This measure is another great innovation. Where these systems have been in place previously, once the list is set up, it has been closed to new entrants. Now, new entrants will be permitted throughout the operation of the market.
Subsection (7) says that the membership of a dynamic market cannot be limited to specific numbers of suppliers and the conditions of membership cannot be amended during the lifetime of the arrangement.
Clause 37 outlines the rules on removing suppliers from a dynamic market. Any supplier that is on the debarment list for a mandatory exclusion ground must be removed from a dynamic market under subsection (1). It would be entirely inappropriate for suppliers subject to debarment on that basis to remain on a dynamic market.
Subsection (2) allows contracting authorities to remove a supplier from a dynamic market if it is an excluded supplier or has become an excludable supplier, or it is discovered to have been an excludable supplier when it applied for membership. Additionally, if the conditions of membership are no longer met, the supplier may be removed from the dynamic market. That provides contracting authorities with flexibility to manage their dynamic markets as they best see fit. Subsection (4) states that, before being removed from a dynamic market, a supplier must be told in writing of the decision and the reasons why.
Clause 38 sets out when fees can be charged to suppliers that participate in dynamic markets, including utilities dynamic markets. Subsection (1) allows for fees to be charged when a supplier is awarded a contract under a dynamic market—other than a utilities dynamic market, which is addressed separately. That avoids “pay to play” arrangements and ensures that fees are only chargeable if the supplier is awarded work. The fees must be calculated as a fixed percentage of the estimated value of the contract awarded. For utilities dynamic markets, subsection (2) states that fees may be charged in connection with obtaining and maintaining membership of the market.
Clause 39 sets out the transparency requirements for the creation and management of dynamic markets. Subsection (1) states that the notices are referred to as dynamic market notices. Subsection (2) requires contracting authorities to publish a notice before they set up a dynamic market. The notice must detail the authority’s intention to establish the market. A notice is also required, under subsections (3), (4) and (5), once the dynamic market has been established or modified, or when the market ceases to operate. Additional content requirements for the various notices will be set out in secondary legislation under clause 93. Clause 39(6) states that private utilities are not required to issue a notice when a utilities dynamic market ceases to operate.
Clause 40 speeds up procurements and reduces the burden for utilities using a utilities dynamic market, or UDM, by only requiring utilities to provide tender notices for upcoming procurements to suppliers already on a UDM, or appropriate part of a UDM, instead of having to publish the notices. In practice, that means utilities can, for example, provide the tender notice to suppliers on the UDM as part of the associated tender documents as each procurement under the UDM is commenced.
In order to take advantage of that flexibility, the notice setting up the UDM must meet minimum information requirements, which will be set out in regulations under clause 88. Utilities must specify in the UDM notice that only members of the UDM will be provided with tender notices. The notice setting up the UDM will be published continuously and will remain open so that new members may join at any time. If accepted, they would then be entitled to receive future tender notices.
Clauses 34 to 40 relate to dynamic markets. Dynamic markets expand on the existing dynamic purchasing system scheme by allowing such markets to be used for all procurements. That means that a reliable and ready pool of bidders can be gathered, which the contracting authority has verified meets the conditions of participation for the contract. When used correctly, such market innovations help save contracting authorities significant amounts of money and time by requiring early scrutiny only once for similar contracts.
Labour does not oppose the proportionate use of that mechanism. However, we note that those who supplied written evidence to the Committee picked up on some concerns. The Local Government Association, in its submission, outlined concerns about terms that are present in the current system but missing in the Bill:
“Councils use dynamic purchasing systems to effectively deliver a range of services that need to be procured quickly, for example, adult’s and children’s residential social care, apprenticeship training, asbestos removal, cleaning services, home-based care services etc.
In particular, local authorities heavily rely on DPS for school transport procurement, where a significant number of contracts must be let quickly each summer as children are allocated school places. These contracts are straightforward, with pre-approved suppliers typically competing on price. These contracts have no cross-border implications so don’t disadvantage operators in other countries as no operator without a local base is likely to bid.
Regulation 34(12) of the Public Contracts Regulations 2015 states: ‘Sub-central contracting authorities may set the time limit for the receipt of tenders by mutual agreement between the contracting authority and all selected candidates, provided that all selected candidates have the same time to prepare and submit their tenders.’
The Bill no longer allows this, and should therefore be amended to reinstate this important flexibility, to ensure that everything from school transport to social care services can be delivered on time for the individuals who rely upon…them”.