Nuclear Energy (Financing) Bill

Dan Poulter Excerpts
2nd reading
Wednesday 3rd November 2021

(2 years, 5 months ago)

Commons Chamber
Read Full debate Nuclear Energy (Financing) Act 2022 View all Nuclear Energy (Financing) Act 2022 Debates Read Hansard Text Read Debate Ministerial Extracts
Alan Whitehead Portrait Dr Whitehead
- Hansard - - - Excerpts

Interestingly, the Climate Change Committee, which has looked into this matter in great depth, considers that in the overall long-term future make-up of our energy mix, about 8 to 10 gigawatts of standby power—therm power—is likely to be required in the shape of new or existing nuclear power stations. That is about the size of the difference with an overwhelmingly renewable but variable economy, with elements of firm power backing it up.

I have mentioned that one plant only that would be included in the suggested 8 GW to 10 GW is in prospect for a start before the late 2020s, because every other proposal has fallen away. However, it is not financed and is probably not financeable by private capital. It is only part financeable by a state financer, with which we do not now want to do business. Let us be clear before we go any further: this Bill is about finding a formula to fund and build Sizewell C power station. Whatever its generic pretensions, that is the issue we should be concentrating on. Even so, getting that plant going would cover most of what the Climate Change Committee considers is the presence in the mix needed.

Dan Poulter Portrait Dr Dan Poulter (Central Suffolk and North Ipswich) (Con)
- Hansard - -

Before the hon. Gentleman moves on from discussing the financing for Sizewell C, does he agree that it is important, when we are talking about financing, that the financing is not just in place for the build of the power station itself, but for the necessary infrastructure and mitigation measures for the local communities in the area, who will be suffering from construction traffic and the like for potentially a 12-year period?