Wednesday 12th February 2020

(4 years, 2 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Anne Marie Morris Portrait Anne Marie Morris (Newton Abbot) (Con)
- Hansard - -

I am pleased to have an opportunity to speak in the debate. I draw hon. Members’ attention to my entry in the Register of Members’ Financial Interests. I have individuals in my constituency who have apartments and houses with cladding problems, some of which is ACM—aluminium composite material—cladding and some of which is not; I live in one that has an ACM problem, so I am close to the issue. The problem has been well articulated, and I totally agree with the comments and the explanation of the right hon. Member for Leeds Central (Hilary Benn), which were clear. In my three minutes, therefore, I will turn to some of the things that could and should be done differently. Clearly, it is about not just ACM cladding. The Government need to redefine what is covered, which must be everything that makes a building a fire risk.

The size of the pot is too small, as I can assure the Minister from personal experience. From personal experience, too, the portal is impossible to use, unless people have experts in IT and surveying in their leasehold community. The Government expect exhaustion of all other legal recourse, but that is expensive and timely, and most leaseholders have neither the pockets nor the ability. The Government ought to take over those claims so that, effectively, they give the money then take over the right to the claims against anyone they think they can make a claim against. The Government have appointed a regulator, which is brilliant, but we do not have the regulations. We are trying to comply with regulations, but we do not know what they are. They need to be expedited.

The timeline for the work to be done is far too short, which I know from personal experience. The block I am most familiar with has reached phase 2. We are required to give collateral warranties. While warranties are fairly standard, these are being given in favour of the Government, not of the leaseholders, which seems mad. Are the Government seeking to take a lien on the property? Such warranties are normally underpinned by insurance, but no insurance company will touch these with a bargepole. If the Government want this to work, they need to step in with an insurance solution. The state aid forms, which have already been referred to, are difficult and complex. That needs to be addressed. To expect every leasehold owner in every building to complete one is unrealistic.

The Government should step in with the banks, particularly for those with existing mortgages, where the banks are saying, “We will not allow you to borrow more, even at the same rate for this work”—even though it is my security that is being affected, which is the bank’s security. It makes no sense. At the very least, we should require the banks to lend the money to those who already have mortgages, for a start. Likewise, for insurers—insurers will not insure anything to do with cladding—the Government must step in and make it clear that it cannot be a valid exception or exclusion.

There is no point charging VAT, then the Government paying it out again. VAT should be taken off. We should also remember that suppliers in this market are growing in number and that is putting prices up, which needs to be fixed.