Draft Electricity Capacity (Amendment) (No. 2) Regulations 2015 Debate

Full Debate: Read Full Debate
Monday 12th October 2015

(9 years, 2 months ago)

General Committees
Read Full debate Read Hansard Text
Andrea Leadsom Portrait The Minister of State, Department of Energy and Climate Change (Andrea Leadsom)
- Hansard - -

I beg to move,

That the Committee has considered the draft Electricity Capacity (Amendment) (No. 2) Regulations 2015.

May I say what a pleasure it is to serve under your chairmanship today, Mr Percy? The regulations amend the main secondary legislation package for the capacity market scheme, which was part of the electricity market reform programme in 2013. The powers to make this implementing secondary legislation are found in the Energy Act 2013. Following scrutiny in this House and the other place, the 2013 Act received Royal Assent in December 2013, with cross-party support. The two changes in the regulations will simplify the process for applicants to the capacity market and were overwhelmingly supported by respondents to our consultation.

Before I explain the changes in more detail, it may be helpful if I say a few words on the background of the capacity market as a reminder to hon. Members, particularly new hon. Members. The capacity market will address our medium-term electricity needs and ensure that there is sufficient electricity supply towards the end of the decade and beyond. In brief, the capacity market will achieve that by making a regular capacity payment to providers that are successful in capacity auctions. In return for that payment, providers must meet their obligations to provide supply or reduce demand when the system is tight, thereby ensuring that enough capacity is in place to maintain security of electricity supply.

Ensuring that families and businesses across the country have secure, affordable energy supplies on which they can rely is our top priority. That is why, working closely with National Grid and Ofgem, we already have firm mechanisms in place to maintain comfortable margins in the system for coming winters. Beyond that, it is essential that generators have confidence that they will receive the revenues they need to maintain, upgrade and refurbish their existing plant, as well as to finance and build new plant to come on stream as and when existing assets are retired. Equally, we want to ensure that those who can shift demand for electricity away from periods of greater scarcity without detriment to themselves and the wider economy are incentivised to do so. That is why we have the capacity market.

The first auction, which was held in December 2014, saw a good outcome for consumers. Fierce competition between providers meant that we obtained the capacity we will need in 2018-19 at prices below the levels that many had expected, and that translates to lower costs on consumer bills.

The regulations make two minor changes to improve the capacity market, based on feedback from stakeholders. The first is to substitute a new definition of “relevant grant” in regulation 17 of the Electricity Capacity Regulations 2014. The second is to regulation 59(3) of the 2014 regulations and will extend from five to 15 the number of days in which applicants can submit credit cover after receiving a conditional pre-qualification notice.

The amendment to the definition of “relevant grant” will ensure that grants, which are there to support feasibility studies or research and development in relation to carbon capture and storage, will not preclude participation in the capacity market. The essential feature is that the carbon capture and storage support should not have provided effective material support that would put a provider at an advantage compared with others that did not get that support. That will not be the case for such early-stage grants for CCS purposes. The regulations extend the number of days from five to 15 to enable applicants to have slightly longer to submit credit cover.

My Department consulted on the two changes in March 2015 and received 22 responses. The vast majority of stakeholders who responded were content with the changes proposed. I look forward to hearing what hon. Members have to say.

--- Later in debate ---
Andrea Leadsom Portrait Andrea Leadsom
- Hansard - -

I can only assure the hon. Gentleman that there was no case of wrong wording the first time around. As he will know, the point of not allowing those who are already in receipt of Government subsidies to participate in a capacity market is sound, because otherwise they would effectively be paid for something they were already being subsidised to produce. The implication of being given a grant was not specifically dealt with, so it was not a case of wrong wording; it was more that that was subsequently pointed out and carried sufficient support to be worth making an adjustment.

The hon. Gentleman’s other point was that CCS may not ever take part in a capacity market. I am not aware that we have come to a conclusion on that either way at this point. As he will know, we do not as yet have any deployed carbon capture and storage in this country, but we are looking at it closely, and two competition projects are currently considering their own ability to develop an industry that could be very valuable for the long-term use of fossil fuels.

Question put and agreed to.