Asked by: Amanda Solloway (Conservative - Derby North)
Question to the Department for Transport:
To ask the Secretary of State for Transport, if he will make an assessment of the potential merits of the proposed A52 improvement programme.
Answered by John Hayes
Highways England, in accordance with its Delivery Plan, is delivering the A52 scheme in Roads Investment Strategy Period 1 (2015-2020) and plans to start construction by 2019/20. The scheme will deliver a package of measures to improve junctions along the A52 near Nottingham to assist with the development of the Nottingham Enterprise Zone adjacent to the A52.
Highways England has appointed design consultants to work up and assess a range of options and will be engaging stakeholders in the coming months.
Asked by: Amanda Solloway (Conservative - Derby North)
Question to the Department for Transport:
To ask the Secretary of State for Transport, when he expects work on the electrification of the Midland Mainline to resume; and if he will make a statement.
Answered by Claire Perry
On 25th June the Secretary of State announced that work on Midland Main Line electrification was being paused pending Sir Peter Hendy’s proposals this autumn on re-planning the Control Period 5 programme, at which point the Secretary of State will make a statement to the House. It would be premature to speculate now on the outcome of the re-plan.