All 2 Debates between Viscount Younger of Leckie and Lord Coaker

Shipbuilding: Use of British Steel for Royal Navy

Debate between Viscount Younger of Leckie and Lord Coaker
Tuesday 30th November 2021

(3 years ago)

Lords Chamber
Read Full debate Read Hansard Text
Viscount Younger of Leckie Portrait Viscount Younger of Leckie (Con)
- Hansard - -

The Type 26 construction programme is sufficiently flexible. The noble Lord will know that there are some delays owing to the late delivery of the propulsion gearboxes. The cost of the contract awarded in 2017 to manufacture the first batch of three Type 26 frigates is £3.7 billion. On current plans, HMS “Glasgow” will be in the water by the end of 2022.

Lord Coaker Portrait Lord Coaker (Lab)
- Hansard - - - Excerpts

My Lords, is it not an appalling state of affairs that, with the Government spending billions of pounds on boosting our naval power, we have to go abroad for much of our steel, as the Minister has just told this Chamber? What people want to hear is what the Government are going to do about it. Rather than describing the problem, can he say how we are going to boost the British shipbuilding industry so that British naval ships are built with British steel?

Viscount Younger of Leckie Portrait Viscount Younger of Leckie (Con)
- Hansard - -

Of course, the noble Lord makes a good point: it would be great if ships could be made from British steel. However, as I said earlier, the steel required for the ships being built—both the surface ships and submarines—is highly specialised. He will know that, for example, the fixed steel required for submarine hulls is made in France with Industeel. The steel for the surface ships is there for the UK steel industry, but at the moment it is sourced from abroad.

Ajax Programme

Debate between Viscount Younger of Leckie and Lord Coaker
Wednesday 9th June 2021

(3 years, 6 months ago)

Lords Chamber
Read Full debate Read Hansard Text
Lord Coaker Portrait Lord Coaker (Lab)
- Hansard - - - Excerpts

My Lords, this is my first time at the Dispatch Box as Labour’s defence spokesperson, and I look forward to debating these important matters with the Minister.

Ajax was set to be delivered in 2017 but, despite £3.2 billion being paid out, only 14 vehicles have been delivered—light tanks that cannot fire while moving—and personnel have been made so sick that the testing has been paused. The Defence Committee called this

“another example of chronic mismanagement by the Ministry of Defence”.

As the problem cannot be fixed before it has been identified, as we heard in the other place yesterday, when does the Minister expect to know exactly what is causing the problems of noise and vibration? How many personnel have been adversely affected? When will the reversing restrictions placed on Ajax be lifted? Given that the total fixed cost for the whole project is £5.5 billion and that £3.2 billion has already been spent, is the Minister confident that Ajax can and will be delivered to that total? If so, when?

Viscount Younger of Leckie Portrait Viscount Younger of Leckie (Con)
- Hansard - -

I welcome the noble Lord to the House and his position on the Front Bench. I am pleased to answer the questions that he has posed. First, as he will know, in any complex acquisition, there are risks and challenges that must be mitigated against, and, in the case of Ajax, we face different challenges due to the nature of such capabilities. Delays can be for a range of reasons, including the technical challenges and programmatic issues.

On the matters that the noble Lord raised and those relating to speed restrictions—which have been publicly aired—the rear step and the question of firing on the move, I reassure the House that we are confident that these will be resolved very quickly. Those issues have been due to the restrictions that were deliberately put in place because we are in the demonstration phase of this project. On the question of noise, and vibration in particular, there is more work to be done. Although I cannot give a date on this, it is obviously an urgent matter and tests are under way at the moment to try to resolve it.

Finally, we have full confidence in the delivery of the whole project. As the noble Lord will know, full operating capability is not due until 2025. That is not to say that there is not a lot of work to be done before then, but we have full confidence in the main contractors, General Dynamics and GDUK, which were selected after a rigorous process and have 60 years’ experience of developing these advanced armoured vehicles.