I hope to reassure the noble Baroness because the factors include, as she is well aware, the gearbox delivery issues for the Type 26. Some flexibility on the timing was allowed for. It is unique, complex and built to extremely fine tolerances, but it has been delivered. We are on time for this programme, for both batch 1 and batch 2. There should be complete reassurance on that front.
My Lords, I also find the Minister’s answer about the Type 26 build rate disappointing, particularly given how long it is before the first Type 26 comes into service. It will certainly see our frigate force level drop to being unacceptably low before the new ships come online. Will the Minister say what level our frigate numbers will sink to before the new ships become operational? That also includes the Type 31.
Again, I reassure the noble and gallant Lord that we have a very clear programme of rolling out shipbuilding. It includes, for the first time, the Type 26s and the Type 31s. It is very important to say, first, that our current capability is absolutely fine and, secondly, that we will have two types of frigate on stream by the end of the decade.
(2 years, 11 months ago)
Lords ChamberMy noble friend makes a very good point. In October 2020 the ONS published a report on UK steel procurement across government. It showed that the reported proportion of steel procured within the UK for public projects was 77%, up from 40% in the previous year.
My Lords, can the Minister say how many countries have committed to acquiring the Type 26 and Type 31 frigates? How many ships are involved? Has this led to a drop in the unit price cost of those ships and will the foreign orders affect the in-service dates of the ships that are for the Royal Navy?
The Type 26 construction programme is sufficiently flexible. The noble Lord will know that there are some delays owing to the late delivery of the propulsion gearboxes. The cost of the contract awarded in 2017 to manufacture the first batch of three Type 26 frigates is £3.7 billion. On current plans, HMS “Glasgow” will be in the water by the end of 2022.
(3 years, 8 months ago)
Lords ChamberMy Lords, it is a pleasure to follow the noble Lord, Lord Browne, on this because I agree with the thrust of his comments. The Bill sets out to make statutory provision about legal proceedings for our Armed Forces when they are or have been engaged in overseas operations, which, of course, is a very laudable aim. However, the Bill’s significant emphasis on the presumption against prosecution as a way of relieving some of the stress of legal proceedings is misplaced. It is the investigation and then the reinvestigation process that so wears people down. A prosecution may even be a form of relief when it comes.
I am sorry to interrupt the noble and gallant Lord, but we cannot hear him very well. We shall come back to him later in the debate.