Baroness Deech Portrait Baroness Deech (CB)
- Hansard - - - Excerpts

My Lords, I support the noble Lords, Lord Blencathra and Lord Robathan, in their attempt to bring some fiscal discipline to this project. Not only has the cost escalated beyond the original estimates without even a spade in the ground; the figures that are available are old. No allowance for inflation has been made. The contingency is far higher than usual. Private funds have not been identified publicly and there is no management control, as pointed out by the National Audit Office.

I am struck by the contrast with the planned expenditure on a fitting memorial to our late Queen, together with a space for pause and reflection, which is reportedly to be sited in St James’s Park. The construction cost is £46 million excluding VAT—including a replacement of the Blue Bridge in the park—and it is going to be ready in 2026. If such fiscal restraint is good enough for our late Queen, surely something has gone adrift in the financial plans for the memorial.

Before the Select Committee on the memorial a few weeks ago, the petitioners asked that the Government should present, for the approval of Parliament, a report on the capital and operating costs of the project, as well as the financial sustainability of the entity that will execute the project and operate it before presenting any new or amended proposal for planning permission. This has not been taken up but it should be.

Originally, the government grant towards this project was £50 million. That was soon raised to £75 million, with £25 million to be raised privately when the cost was estimated some years ago at £100 million. Now, that has nearly doubled. We can assume only that the Government will pick up the entire bill. The latest estimate, made a couple of years ago, is £138 million without contingency and £191 million with contingency. There is no information about who will do the building—indeed, whether there are any builders willing to do it, given the security risks.

There are gaps in our financial knowledge. The Commons Select Committee commented on this, saying:

“We are particularly concerned about the costs around security of a Memorial and Learning Centre, which would need to be taken into account. Security is likely to be required around the clock, and this is, as yet, an unknown cost. Security is likely to become an expensive additional cost, which we urge the Government not to overlook”.


Construction costs are bound to rise because this is an historical site very close to the river. It oozes underfoot when you walk through it in the rain and it squelches. It is a fair bet that obstacles relating to water and archaeological finds will emerge if digging ever starts.

About £20 million has been spent so far, I believe, with nothing to show for it; nor has inflation been accounted for. A specific charity is fundraising for the private element but we have heard nothing about its success. Can the Minister tell us how the funding has now been settled, including how much has been raised privately and from where?

In 2022, as we heard, the NAO delivered a report that was highly critical of the department’s performance. It was particularly anxious about management. It noted the failure to consider an alternative site. All this got a complacent response from the department that all was well, with no changes in management and no transparency. Operating costs are also a mystery. The Government have pledged free entry to the learning centre—provided, of course, that visitors book in advance online. Operating costs so far are estimated to have risen to £8 million a year and the cost of security is a big unknown. The Government had hoped to make some money from the learning centre by opening it for conferences, even in the evening, but it would be a most unattractive site: open to the elements; open to risks of various sorts; and calling for expenditure to run it out of hours, not to mention disturbance to the neighbours.

Can the Minister tell us about the operating costs and what plans there are to commercialise the space? The Infrastructure and Projects Authority has three times rated the project as “red” and “undeliverable”—most recently, just a few weeks ago—in the same bracket as HS2. The Minister believes that this is because planning permission has not been granted, but that is mistaken because the authority has reported three times in three years on this and, during one year of that, there was planning permission before it was quashed. Anyway, if not having planning permission was the important factor, why is HS2 regarded as “red” and “undeliverable”? This is a quasi-HS2 project.

An important recommendation in the Prime Minister’s report in 2015 on remembering the Holocaust was that there should be an endowment fund. This was to be used to

“support Holocaust education around the country for generations to come”,

to support

“local projects and travelling exhibitions”,

and to ensure that the learning centre would be

“at the heart of a truly national network of activity”.

The report said:

“In administering the endowment fund, the Learning Centre’s trustees would be expected to ensure maximum value for money. This would include requiring organisations to work together more collaboratively across the network, removing duplication and enhancing the impact of the whole sector”.


Have the Government made an allowance for this in their cost calculation, and if not, why not?

The Commons Select Committee on the Bill commented:

“It seems to us that the true cost of this project has not been established. We note that it is not unusual for the costs of major projects to increase with time, due to unforeseen building issues, the ambition of the project, and increases in inflation. The longer that building works go on, the more expensive this project will become. On this basis, we urge the Government to consider how ongoing costs are likely to be paid for and whether it offers appropriate use of public money”,


which it clearly does not. This amendment seeks to cap the costs to force proper management of the project and bring it into a reasonable financial framework. It also proposes a normal contingency fee rather than an extraordinary one.

This Government pride themselves on financial management, and now is their chance to demonstrate that. If the Government will not accept this amendment, will they meet the signatories to the amendment and show transparency about the cost calculations and where they are going?

Viscount Eccles Portrait Viscount Eccles (Con)
- Hansard - -

My Lords, I have a clause stand part Motion in this group. I am a neighbour of Victoria Tower Gardens, I live with my wife in Smith Square and I was a petitioner to the House of Lords Committee.

After what my noble friend Lord Blencathra told us, as well as the noble Baroness, Lady Deech, I will try to be short. My purpose is, and always has been, just to set out the contrast between what was put on the tin in January 2015 and what is on the table now. As my noble friend Lord Blencathra said, they are very different, and I think it will help the Committee if they can be clear about what the differences are.

In January 2015, my noble friend Lord Cameron said:

“Today—with the full support of the Deputy Prime Minister and the Leader of the Opposition—I am accepting the recommendations of the … Commission”.


You could not be clearer than that, and later, in his Statement in the House of Commons, he reiterated that. I suppose—because I do not think we have ever been told—that after 10 years, nine and a half of which, of course, were under the previous Administration, that undertaking is still in existence, so we are going to carry out the recommendations of the commission.

There were five recommendations from the commission, and the first was that there should be a “striking memorial”. Its very first qualification of that was that it should be

“a place where people can pay their respects, contemplate … and offer prayers”.

I rather doubt that what is on the table now—which I gather as best I can from Clause 1 and the Explanatory Memorandum—is a suitable place for paying respect, contemplating and praying. As I understand it, the people visiting will be expected to move through in something like half an hour.

You can make an argument, which I will later, that this is not a suitable memorial. Remembering people is a private affair. The Holocaust was 6 million Jewish tragedies. It is not to say that this is, as we would expect, a London-based conventional memorial. It is something different. In its report, the commission in no way indicated that the memorial would be manned or that there would be interactivity at the memorial. It is clearly set out as a conventional memorial, in a long paragraph.

The second recommendation, about the learning centre, is much longer. It has a huge text. It is clear that the commission did not expect that to be done in five minutes. It did not see this as part of the memorial. There was mention of a campus. As the noble Baroness, Lady Deech, said, it is not the same thing but a completely different activity. Yes, the commission said that it should be close to the memorial, but that closeness depends on where you choose to put the memorial. As the noble Baroness said, the commission proposed three big sites and on all of them it would not have been difficult to put the learning centre and build it up over the years as a campus. It also said that the money for that should be raised immediately.

The third recommendation was for an endowment fund. We all know that endowment funds are not easy. They are very difficult things. It is clear that the commission saw the fund as being for, as the noble Baroness said, the development of the learning centre. The fourth recommendation was that records should be brought up to date. Out of the £20 million that has been spent, a certain proportion has been spent on records of “survivors and liberators”, to use the commission’s words. However, we do not know what has been collected and I cannot see why we have not been able to see some of that work. It is not dependent on the construction of David Adjaye’s building in Victoria Tower Gardens.

Finally, in two places—in Mr Davis’s summary and in the commission’s summary—it is said that an immediate executive independent body should be formed. There was an effort to start one by the Cabinet Office and the Prime Minister—who, we must remember, was there for only some 18 months after his January statements before he resigned. Clearly, when Sir Peter Bazalgette was appointed to the foundation, it was in mind that it would be executive. He secured the Victoria Tower Gardens position and held an exhibition—and showed us the result. However, in April 2018, quite a long time after the Prime Minister, my noble friend Lord Cameron, had made way for my noble friend Lady May, he resigned. We do not know why he resigned, or why the body then formed under my noble friend Lord Pickles was made advisory. One can speculate but it has never been explained why there was a change from the proposal of an executive body to one for an advisory body. The fact is that nobody is accountable for managing this project.

There is such a serious difference between what was on the tin in 2015 and what is in front of us now that it needs to be thought about again. It seems to me that the new Government, who have been looking at this whole issue as accountable only for the past seven months, are in a very good place to review it and, if it requires change, to make those changes.

--- Later in debate ---
Lord Khan of Burnley Portrait Lord Khan of Burnley (Lab)
- Hansard - - - Excerpts

My Lords, the Committee can understand that I do not agree with that point. That is a matter of opinion for Sir Richard Evans. Everyone is entitled to their opinion, as we have seen in the passionate debate today.

I was making the point that several noble Lords may have had the opportunity to see a short presentation from Martin Winstone, the historical adviser to the programme, in which he provides a small insight to the work under way. For those noble Lords who have not seen it, we can arrange for Martin Winstone to come in and give them that presentation. I had a drop-in session yesterday; unfortunately it was just me and officials, but I enjoyed it.

The overall focus of the learning centre must of course remain clearly on the Holocaust, and it must be wholly integrated with the national memorial to the 6 million Jews murdered in the Holocaust. We want to be sure that visitors are left in no doubt about the nature of the Holocaust. Having seen the memorial, they should clearly understand what it represents. For those reasons, it simply does not make sense to envisage a learning centre located elsewhere and carrying a much broader set of messages.

The history of the Jewish people is rich and deep. Jewish communities have a long history in Britain that needs to be understood, including of course the history of anti-Semitism, extending for many centuries. Telling such a story requires expertise, creativity and space. The Jewish Museum London told this story well, making excellent use of the tens of thousands of artefacts in its collection. I wish the museum well in its search for a new home. I believe also that there will be important opportunities in future for joint work between the learning centre and the Jewish Museum. We aim to work in partnership with institutions across the UK and overseas as we develop education programmes, and as we encourage greater awareness of the Holocaust and its deep roots. But I am sure that we should recognise the differences between the purpose of a Jewish museum in London and the aims of a learning centre located with a Holocaust museum. Each has a distinct and hugely important aim. Placing the Holocaust learning centre wholly within the Jewish Museum could easily mean a loss of focus and would certainly require breaking the essential link between the learning centre and the memorial.

Viscount Eccles Portrait Viscount Eccles (Con)
- Hansard - -

Who is the “we” who will work with these other institutions? Because, as noble Lords will know, as we come on to the next group, if we do, there is no management. Therefore, I do not understand who is going to work with these other institutions.

Lord Khan of Burnley Portrait Lord Khan of Burnley (Lab)
- Hansard - - - Excerpts

My Lords, I mean “we” as in the Government. Can I continue my final point? The noble Baroness, Lady Scott, made the very important point about rising anti-Semitism. Let me be clear. Anti-Semitism is completely abhorrent and has no place in our society, which is why we are taking a strong lead in tackling it in all its forms. The Government are particularly concerned about the sharp rise in anti-Semitism and will not tolerate this. We have allocated £54 million for the Community Security Trust to continue its vital work until 2028, providing security to schools, synagogues and other Jewish community buildings. We have been actively exploring a more integrated and cohesive approach to tackling all forms of racial and religious hatred. We continue to work closely with the noble Lord, Lord Pickles, in his important work of IHRA. Also, the noble Lord, Lord Mann, continues his work as an anti-Semitism adviser to the Government. On that note, I respectfully ask my noble friend Lady Blackstone to withdraw her amendment and not move her other amendments in this group.