(5 days, 12 hours ago)
Grand CommitteeI politely disagree with the noble Baroness—there is no inconsistency. My job in promoting the Bill is to look at the two main clauses along with the third one, which says that the Bill applies to England and Wales. Planning permission is absolutely for the designated Minister. As a proposal of national significance, it is perfectly proper for a planning decision to be taken by a Minister rather than by a local planning authority. When these arrangements were challenged in a judicial review in 2020, that challenge did not succeed.
Perhaps I can just make some more progress. Like any other neighbour, Parliament can make its views known through the planning system.
With the greatest respect to the Minister, if the Planning Minister is somebody different, why is he not here answering these questions today?
My Lords, that is not the way planning works. I will leave my remarks there, in the sense that it is up to the designated planning Minister how he takes this process forward, but there will be a planning process, which is right. It is not ideal for this House, through this Bill in particular, to be discussing planning applications. That is not the role of this Committee on this Bill in particular.
As I said before, Parliament can make its views known through the planning system and can be confident that those views will be given due weight. We have well-established provisions in place to allow a decision to be challenged if proper weight is not given. The Lords Select Committee considered this matter, and the Government were pleased to give an assurance that they would notify the relevant authorities in both Houses as soon as practicable following the reactivation of the planning process in respect of the current application.
(1 week, 5 days ago)
Grand CommitteeI will come back to the noble Baroness’s point towards the end of my wind-up.
Following the planning inquiry, the independent inspector submitted his detailed and lengthy report to the Minister, with a recommendation that consent should be granted. The Minister agreed with that recommendation.
Amendment 16, in the name of the noble Lord, Lord Strathcarron, would simply take us back around nine years and require the design competition to be run again. There is no good reason for such a step. The Government remain fully committed to the current design, which has been the subject of detailed attention and wide consultation. Suggestions that the memorial was not designed by Ron Arad or not envisaged specifically for Victoria Tower Gardens are wide of the mark. Ron Arad’s drawings showing the evolution of the design have been displayed at the Royal Academy for all to see the originality and brilliance of his design.
Does the noble Lord agree that a camel is a horse designed by a committee? What he has just said proves that.
My Lords, swiftly moving on, it is not realistic to suppose that a new design competition would produce a design that pleases everyone. Let me be absolutely clear: I have featured in a BBC housebuilding documentary programme and I was most suspicious of design but, by the end of the 14 months when I was running for the European Parliament, I realised the impact and the power of design. Everyone has different tastes and different suspicions of design; everyone has different views. Differences of view about the artistic merits of designs are nothing new. It is quite proper that there should be an open debate about the design of new memorials, indeed of all new public buildings.
The design that is proposed for the UK national Holocaust memorial and learning centre is the product of extensive consultation, a design competition that attracted many of the best architects in the world and a judging process that relied on the deep expertise of a talented and experienced panel. Are we simply to set all that aside and require the process to be repeated? It is right, of course, that a decision to proceed with construction of the memorial and learning centre should be taken only after all relevant voices have been heard.
A number of noble Lords, including the noble Baroness, Lady Deech, referred to the press reports in 2023 concerning Sir David Adjaye. Following allegations made in those reports, Adjaye Associates has said that Sir David will not be involved in the UK Holocaust memorial project until the matters raised have been addressed.
I am not sure whether the noble Baroness, Lady Fleet, was in her place when I made the following point. The learning centre will look at subsequent genocides through the lens of the Holocaust. The content of the learning centre is being developed by the leading international curator, Yehudit Shendar, formerly of Yad Vashem. The focus is to ensure that the content is robust and credible and reflects the current state of historical investigation into, and interpretation of, the Holocaust. The exhibition will confront the immense human calamity caused by the destruction of Jewish communities and other groups, and the exhibition will also examine the Holocaust through British perspectives.
The noble Lord, Lord Sassoon, said that he knows nothing wiser. I was very clear in an earlier group about the next steps of the process around planning options, subject to the passage of the Bill. I made it very clear last week—and I will say it again after the confirmation of the previous group—that the designated planning Minister, Minister McMahon, will take an approach of his choosing, whether that will be a consensus round- table meeting, written responses or a public inquiry. It is for the designated Minister to decide which approach to the planning process he will take. On his very important focus on world heritage sites, I would not do justice to the noble Lord’s passion in this area if I swiftly gave the answer now, but I will come back to him, and go through this in detail, in the next group.
(4 weeks ago)
Grand CommitteeI understand the point that the noble Lord is making, but this Bill allows expenditure. Funding will be allocated through the normal public expenditure arrangements. The House of Commons passes annual appropriation Acts.
The project is also subject to review by the National Audit Office. In July 2022, the National Audit Office conducted a review and produced a report noting, among other points:
“The programme has controls to try to safeguard against substantial cost increases”.
Three recommendations made by the National Audit Office have been implemented. On the points that the noble Lord, Lord Blencathra, raised about the management of the project, we welcome the National Audit Office’s July 2022 report on the project and have addressed all its recommendations. The National Audit Office also recognises that governance arrangements are in place. The strategic benefits of the programme have been clearly identified and specialists with the necessary skills have been recruited to the programme.
It is also important to make the point that the Infrastructure and Projects Authority, which the noble Lord referred to, currently rates the project as undeliverable because the Bill needs to be passed and planning consent granted in order for it to proceed. That is why there is a red flag rating on this. The project needs planning consent. That was quashed, and it was given a red rating as this Bill needs to be passed.
The £138 million estimate is based on professional advice from cost consultants and allows for inflation.
My Lords, I do not want to limit myself by saying “yes” or “no” because I do not know the answer. As you would expect, I do not have that knowledge here.
On contingency, the estimate considers potential inflation being more than expected and the risks of the site. Again, the estimate is based on professional advice.
The noble Baroness, Lady Deech, raised the commitment to raise charitable donations. The commitment to raise £25 million has been given by the Holocaust Memorial Charitable Trust, which is chaired by Sir Gerald Ronson. Specific donations will be agreed once planning consent has been granted.
The noble Viscount, Lord Eccles, raised improving records. The testimony of 120 Holocaust survivors has been recorded and is being made available online for all to see before the memorial opens. We have worked with the Association of Jewish Refugees to create an online portal.
The noble Baroness, Lady Deech, also talked about the operating costs. These have been estimated at £6.5 million to £8 million per annum.
My Lords, I was responding to the point made by the noble Baroness, Lady Deech, on the operational costs. Operating costs have been estimated at between £6.5 million to £8.5 million per annum, and the estimates draw on comparisons with other museums and galleries of a similar size. Further detailed costs will be developed as the programme proceeds.
If those costs have been estimated in line with other museums, do they include the extra costs that will be needed for potential demonstrations at that particular memorial, especially as it is so close to Parliament?
Yes; all the costs associated with the operation of the memorial learning centre reflect the estimation I have just detailed, but further details of costs will be developed.
On the point from the noble Lord, Lord Lisvane, on the Explanatory Notes and re-erection, the purpose is to avoid having to come back to Parliament to change legislation in the event of damage and related issues. We have regular discussions with the Palace of Westminster on the issue of other works, including the restoration of Victoria Tower. These will continue to take place and we expect to manage logistics, deliveries, and so on, through sensible planning. The estimated cost of the UK Holocaust memorial and learning centre has been produced in line with the Treasury Green Book guidance. Taking all that into account, the last accounting officer assessment from June 2023 concludes that the project represents value for money. The ordinary mechanisms by which Parliament allocates public funding and holds Ministers to account can apply to this programme, just as with any other programme.
The further Amendment 27, proposed by the noble Lord, Lord Blencathra, would introduce an additional step in the process of seeking planning consent for the proposed Holocaust memorial and learning centre. While the noble Lord is to be commended for his focus on cost control and value for money, the additional step he proposes is not necessary and would simply add still further delay to the decision-making process. Costs are regularly reviewed, and updated figures will be published in due course, in line with the Government’s major projects portfolio reporting process.
A range of options are being considered for operating the memorial and learning centre. As a significant public investment, responsibility for managing the centre will need to rest with a body that is ultimately accountable to Parliament. The Government will continue to be transparent about the costs and future arrangements for the Holocaust memorial and learning centre. This should, however, not delay the separate planning determination process.
The Holocaust memorial and learning centre will be a source of pride and an inspiration to the whole of society across boundaries of religion, class, geography or political party. I have only to quote the words of 94 year-old Holocaust survivor Mala Tribich, MBE, to underline why this is so vital:
“As the Holocaust moves further into history and we survivors become less able to share our testimonies this Memorial and Learning Centre will be a lasting legacy so that future generations will understand why it is important for people to remember the Holocaust, to learn from the past and stand up against injustice”.
I just want to echo—