It is a pleasure to serve under your chairship, Mr Efford. I heartily congratulate my very good and hon. Friend the Member for Carlisle (Ms Minns) on securing this debate on the anniversary of the Settle-Carlisle railway, and I thank other Members for their contributions.
I am grateful to my hon. Friend for her continued advocacy on behalf of her constituents. This is a moment of celebration of our railways, but it is also a time to reflect on the present and the future. I welcome the opportunity to address some of those points today.
The Settle-Carlisle railway, which is celebrating its 150th anniversary, is, of course, one of the most historical and spectacularly scenic lines in the UK, with a long and colourful history of innovative engineering and dogged determination by the rail visionaries who fought to keep the line open against all the challenges it has faced—a legacy that my hon. Friend is certainly working hard to continue.
I am delighted to assure my hon. Friend that the future of the line is indeed secure. The introduction of the Yorkshire Dales Explorer has brought thousands of new visitors to the line, investment at Horton-in-Ribblesdale station and secured the line’s invaluable role as a support route for the west coast main line. These all demonstrate the line’s ongoing importance to our network and this Government’s commitment to its future.
I am pleased that there is such a strong community rail involvement with this historical line. Community rail is all about connecting communities to the railways, and at the heart of the community rail concept are community rail partnerships. The Settle-Carlisle Railway Development Company has done some wonderful work in this area. It has been an accredited community rail partnership for more than five years, working to support the local economy and benefit communities along the line.
Its work includes organising station open days and art installations, running projects to support access to the railway and environmental initiatives with community organisations, as well as providing a range of services and products that benefit locals and visitors alike. The company achieves so much for the benefit of communities along this historical line. I congratulate it on its most recent reaccreditation, awarded in recognition of its community-centred projects and services provided across the Yorkshire dales and Cumbria.
I also pay tribute to the work of the Settle and Carlisle Railway Trust, which does so much valuable work in helping to restore, preserve and maintain the historical buildings and structures along the route, sparking the imagination and engagement of the public.
The railways, of course, have changed so much since the first passenger trains on the Settle-Carlisle line, and I think it is appropriate to raise where this Government see the future of this railway. Rail reform will put passengers and customers back at the heart of the rail network. The Railways Bill, of which I know my hon. Friend is a keen supporter, is progressing through Parliament and will create Great British Railways, which will bring track and train together under one publicly owned and accountable body to reduce fragmentation and improve decision making. GBR will work closely with local mayors and local authorities to make sure that services meet the needs of their areas and better integrate with other modes.
I now turn to Northern Trains and its performance as the main operator on the Settle-Carlisle line. I am pleased with the introduction of the Yorkshire Dales Explorer, which links Greater Manchester and Lancashire to the Settle-Carlisle line and the dales. I also hope that my hon. Friend’s constituents are able to partake in Northern’s offer of discounted tickets between Leeds, Settle and Carlisle, in honour of the 150th anniversary. But that does not mean there is not more work to do.
Northern’s performance leaves room for improvement. We have an improvement plan that outlines the steps that the operator will take to improve reliability, with a target of 90% of all its trains arriving within three minutes of timetable and cancellations below 2%. I am pleased that the latest rail period results show that cancellations on the Leeds-Carlisle route were only 1.24%, but we need to work to improve punctuality, with 77% of trains arriving within three minutes of timetable. I look forward to working with my hon. Friend to improve services for both tourists in her remarkable area and her constituents. Northern is also in discussions with train manufacturers to procure new train sets to replace the oldest trains in its fleet. The procurement of up to 450 new train sets will offer increased capacity as well as more accessible trains for passengers.
In January and April this year, the Settle-Carlisle route played a critical role in supporting passengers during several closures of the west coast main line for engineering work. To avoid lengthy replacement bus journeys, Avanti West Coast operated its bi-mode Evero trains over the historical route—the first time in more than a decade it has been used for that purpose. Feedback was incredibly positive, underlining findings from the rail watchdog, Transport Focus, that passengers prefer to stay on trains than take replacement bus services—that is certainly my preference, too—even if it involves a longer journey. Avanti hopes that the Settle-Carlisle route can continue to play an important role as a diversionary route over the next decade, especially when a significant volume of renewal activity is required on the northern section of the west coast main line.
On infrastructure, Network Rail recently installed a footbridge with lifts at Horton-in-Ribblesdale station, allowing the closure of a high-risk level crossing and enabling a rail connection to the nearby quarry. The scheme was a mix of public and private investment, including a contribution from the quarry along with the Access for All fund. Connecting the quarry by rail safeguards the future of the facility while reducing carbon emissions by taking lorries off the road.
The 150th anniversary of the Settle-Carlisle line is an opportunity not only to celebrate extraordinary railway heritage, but to recognise wider investment to ensure that rail continues to support communities, connectivity and economic growth for generations to come. That investment includes the £323 million west coast north modernisation programme, which is the biggest improvement programme on the northern section of the west coast main line in decades.
Network Rail and industry partners are working together, in the spirit of Great British Railways, to keep passengers moving while replacing ageing infrastructure, particularly the overhead line equipment that powers electric trains. Over the past two years, Network Rail has renewed around 200 km of overhead wires on the northern sections of the west coast main line. The work will improve reliability and deliver a more resilient and better-connected railway for passengers and freight. From the Settle-Carlisle line to the west coast main line, rail remains a vital part of connecting people, places and opportunities across the north and Scotland.
My hon. Friend will recall the Department’s investment of £13.5 million as part of the £38 million Carlisle station gateway project, part funded by the borderlands inclusive growth deal and delivered in partnership between Network Rail and Cumberland council. The scheme provides a new public square to the rear of the station, an enhanced Court Square to the front, new lifts and increased car parking capacity. Works are on site and the Scott & Brassey public house has now opened in the restored first-class waiting room, with passengers enjoying a selection of great local ales. I often travel up to Glasgow, and I will avail myself of those great local ales as soon as I make contact with Carlisle station.
To conclude, I assure my hon. Friend that the Government are firmly committed to honouring our railway heritage and improving services for passengers in rural communities across the north. She continues to be a resolute champion of the Settle-Carlisle railway, and the Government are committed to supporting her and her constituents as she continues to do so. Here is to the 150 years to come.
Question put and agreed to.