Monday 2nd December 2024

(3 days, 2 hours ago)

Written Statements
Read Hansard Text Read Debate Ministerial Extracts
Angela Rayner Portrait The Secretary of State for Housing, Communities and Local Government (Angela Rayner)
- Hansard - - - Excerpts

More than seven years after the Grenfell Tower tragedy, too many buildings in England still have unsafe cladding and the speed with which the problem is being addressed is far too slow. Only 30% of buildings identified in England with unsafe cladding have been fixed, with potentially thousands to be identified. As the remediation process drags on, residents continue to face distress, uncertainty and rising costs as they wait for action. This situation is completely unacceptable and must change.

For the first time, we have set firm targets for this important work. By the end of 2029 all buildings 18 metres and above with unsafe cladding in a Government-funded scheme will be remediated, and all buildings 11 metres and above with unsafe cladding will either have been remediated or have a completion date, or the landlords will be liable for severe penalties.

To drive this progress and ensure we meet these targets, I am today publishing our new remediation acceleration plan which sets out decisive measures so that buildings with unsafe cladding are fixed faster, remaining buildings still at risk are identified and residents are supported throughout the process. The remediation acceleration plan will be deposited in the House Libraries.

Many of the highest risk buildings are known to us. We must ensure they are urgently fixed. We intend to introduce new legal obligations on landlords to remediate unsafe cladding, with severe penalties, including criminal and civil sanctions for inaction. We also intend to provide further powers and resources to regulators so that bad actors are held to account.

We recognise the power of collaborative working and will drive co-ordination between regulators including through empowering metro mayors to lead local acceleration plans. Work is already under way with mayors being supported to play a new crucial role in driving remediation progress by leading local remediation acceleration plans alongside partners in local government, and this Government are determined to support and work effectively with mayors and combined authorities, who know their areas best, to deliver for residents.

Our plan sets out measures to accelerate cladding remediation in the social housing sector. From April 2025, we will also increase funding for social landlords applying for Government remediation funding so that remedial works can start sooner. We will work with social housing providers and regulators to agree a long-term strategy for social housing remediation, to be announced in spring 2025.

We are also publishing a joint plan that commits developers for the first time to stretch targets to assess all of their buildings by July 2025, to start or complete remedial works on 80% of their buildings by July 2026, and on all their unsafe buildings by July 2027. To meet these targets, developers will need to more than double the pace at which they have been assessing buildings and starting works so far this year. At least 28 developers have already endorsed the joint plan, covering over 95% of the buildings that developers need to remediate. We welcome the commitment that developers have made.

Developers have also agreed to expedite their work with social landlords to resolve contributions they should make towards works to make social sector buildings safe. This will mean that remedial works on affected social sector buildings will start sooner.

We will also ensure that the burden of paying for fixing historical building safety defects does not fall on leaseholders or further burden taxpayers. We intend that the building safety levy will come into effect in autumn 2025 and will be charged on all new eligible residential buildings in England. The levy will raise around £3.4 billion for remediation and help to ensure that those who are responsible for the building safety crisis help pay to put it right.

There is a long way to go to be confident that all buildings with unsafe cladding have been identified. Those responsible for their buildings’ safety are failing to come forward to make their buildings known. There is a requirement to register buildings above 18 metres, but there is currently no single register that records all relevant buildings, and so identifying these buildings is a complex task. Through this plan we intend to introduce new legislation to drive action from those responsible for their buildings’ safety by tightening building assessment requirements and to create a comprehensive building register so that all relevant buildings can be more quickly identified.

However, we cannot wait for this change to start to make progress. We expect to have reviewed 175,000 Ordnance Survey building records for potential buildings at 11 metres in height and above by the end of March 2025. Through this approach, we expect to have reviewed 80% of the 11 metre-plus building stock, contacting responsible entities for those we believe might have a cladding risk concurrently, with plans to increase this to over 95% by late 2025.

We will share data with metro mayors, combined authorities and local regulators so that, when required, they can take action locally to ensure buildings are identified and remediated quickly. Residents who believe that their building may be unsafe can report this to regulators, or directly to us through the “tell us” tool.

This Government are clear that much more needs to be done to better protect blameless residents. All remediation projects should adhere to and evidence their compliance with the code of practice for the remediation of residential buildings.

We will introduce new measures to support residents with the costs they face.

This includes new shared ownership guidance allowing leaseholders to sub-let their properties at market rates so that they are no longer penalised for issues that are no fault of their own and an updated process to limit the number of valuations that shared owners have to pay for when selling their homes. Social landlords continue to have the option to buy back homes where shared owners are unable to sell due to building safety issues.

Buildings insurance premiums are unacceptably high for too many leaseholders in buildings with fire safety issues. The Government will therefore work with insurers to consider whether, for the duration of remediation programmes, Government might support the industry to reduce fire-related liabilities in order to reduce the high insurance bills leaseholders are facing. We are also launching a public consultation on the introduction of a fair and transparent fee for leaseholders to pay to those who manage insurance for their buildings.

This Government have already reopened the waking watch replacement fund which has provided alarms in 346 high-risk buildings. We estimate the fund has saved affected leaseholders on average £172 per calendar month and it has played a role in preventing residents being evacuated from their homes. We are extending the waking watch replacement fund until the end of the next financial year, and will confirm long-term plans at the next stage of the spending review to protect leaseholders from costs while they wait for remediation to take place.

Finally, we are taking several actions that address criticisms the Grenfell inquiry report made of the manufacturers of cladding and insulation products. This includes action towards preventing the most egregious companies, found to be part of the horrific failings that led to the Grenfell Tower tragedy, from being awarded Government contracts. It also commits to system-wide construction products reform, including proposals on liabilities, robust sanctions and penalties against manufacturers.

The remediation acceleration plan marks a pivotal moment in addressing the building safety crisis in England. We are taking decisive steps to fix buildings faster, identify all buildings with unsafe cladding, and ensure residents are safe and protected. We will work tirelessly to this end with resident groups and industry. I will provide an update in summer 2025.

[HCWS274]