Monday 2nd September 2024

(2 months ago)

Written Statements
Read Hansard Text
Michael Shanks Portrait The Parliamentary Under-Secretary of State for Energy Security and Net Zero (Michael Shanks)
- Hansard - - - Excerpts

The Minister of State for Energy Security and Net Zero, my noble Friend Lord Hunt of Kings Heath OBE, made the following statement today:

This statement concerns an application for development consent made under the Planning Act 2008 by Ecotricity (Heck Fen) Ltd for the construction and operation of a solar photovoltaic electricity generating station situated in Lincolnshire.

Under section 107(1) of the Planning Act 2008, the Secretary of State must make a decision on an application within three months of the receipt of the examining authority’s report unless exercising the power under section 107(3) of the Act to set a new deadline. Where a new deadline is set, the Secretary of State must make a statement to Parliament to announce it.

The statutory deadline for the decision on the Heckington Fen solar park application was 9 August 2024.

Ecotricity (Heck Fen) Ltd has requested that the Secretary of State extends the statutory deadline to allow time for further negotiations with landowners and to ensure the necessary permissions can be obtained. I have decided to allow a short extension and to set a new deadline of no later than 27 September 2024 for deciding this application for these reasons.

The decision to set the new deadline for this application is without prejudice to the decision on whether to grant or refuse development consent.

[HCWS52]