Kettering General Hospital: Redevelopment

(Limited Text - Ministerial Extracts only)

Read Full debate
Friday 22nd March 2024

(8 months ago)

Commons Chamber
Read Hansard Text Watch Debate
Maria Caulfield Portrait The Parliamentary Under-Secretary of State for Health and Social Care (Maria Caulfield)
- View Speech - Hansard - - - Excerpts

I congratulate my hon. Friend the Member for Kettering (Mr Hollobone) on securing this important debate. He tirelessly campaigns for Kettering, particularly for the new hospital there, and firmly holds Ministers’ feet to the fire on this issue.

I reassure my hon. Friend that the Government remain absolutely committed to a new hospital for Kettering, and that a number of milestones are being met. As he pointed out, the trust is currently developing its refreshed strategic outline business case, supported by the new hospital programme team, to make sure that it aligns with our national approach of standardising all our new hospitals to the Hospital 2.0 model. We expect a submission to the Department for the wider hospital work later this year.

Philip Hollobone Portrait Mr Hollobone
- Hansard - - - Excerpts

I thank the Minister for the start of her response, which has been very constructive. I support the Hospital 2.0 programme and its standardised design of the 40 new hospitals—that is great. Kettering General Hospital has already submitted its first two business cases for the main scheme. Instead of having to resubmit them all over again, please could it simply submit an addendum, so that it does not have to reinvent the wheel?

Maria Caulfield Portrait Maria Caulfield
- Hansard - - - Excerpts

I absolutely take my hon. Friend’s point, particularly given the issue he raised about RAAC being discovered on the maternity and gynae floors. I will take that point to the Hospitals Minister in the other place and the team, and I will put in his request to meet the Minister to discuss this. I understand the frustration that comes when some work has been done already, and that it takes time for the trust, which urgently wants to get on and construct the new hospital. I will certainly take that away after the debate.

I reassure my hon. Friend, his constituents, the patients who use Kettering General Hospital and the staff who work there that the new hospital will be in place as soon as possible and will meet the 2030 deadline. I recognise the urgency. As part of the works, the energy centre is crucial to the development of the wider hospital scheme. We heard very eloquently from my hon. Friend this afternoon—he has also explained this to me and other Ministers—that this is not just a crucial part of the new hospital plans, but that the current system was only ever meant to be a temporary measure; he described how fragile it is, so I recognise the urgency of starting work on the new energy centre.

My hon. Friend will know that early works have commenced on site. Ground clearance and site surveys are under way to prepare for the cabling that is needed to provide the energy centre’s power once it is completed. Hoardings will shortly go up to allow more extensive works to start on site. I can reassure my hon. Friend that his constituents will start to see progress on that very shortly. The trust has made progress, recently reaching a new connection agreement with National Grid and agreeing the reserve capacity needed for the energy centre. That is a vital step in securing the new hospital’s energy requirements for the future and in dealing with the imminent problem of the temporary energy facility that is keeping the hospital going.

The final piece of the jigsaw to get the construction of the energy centre under way is the full business case that the trust needs to submit. I can reassure my hon. Friend that that we are working with the new hospital programme team on this. We expect the case to be submitted in June. The Hospitals Minister has committed that, subject to it meeting the cost threshold and certain criteria, we can estimate a turnaround time for approval of two weeks, so hopefully we will start to see the construction of the energy centre this summer. I hope that gives my hon. Friend and his constituents reassurance.

Philip Hollobone Portrait Mr Hollobone
- Hansard - - - Excerpts

I thank the Minister for her reassurance. The purpose of these debates is to put pressure on the Government—that is the way Parliament works—but would she join me in applying gentle pressure on the trust? The sooner it can get the full business case in, the sooner the thing can be approved and the funds can start to flow.

Maria Caulfield Portrait Maria Caulfield
- Hansard - - - Excerpts

Absolutely. I have spoken to the Hospitals Minister on the specific issue of Kettering, and he is in agreement; if the trust can keep us updated with the timeline and let Ministers know as soon as it submits the business case, he has given the commitment to try to turn it around within a couple of weeks. I would gently say to the trust that it is in its interest to get the case to us as soon as possible.

Philip Hollobone Portrait Mr Hollobone
- Hansard - - - Excerpts

I thank both my hon. Friend and the Hospitals Minister for their involvement. It is right, is it not, that this two-week turnaround is a novel feature of the new hospital programme? It is a groundbreaking approval process that will turn the application round that quickly. Where Kettering leads, others surely will follow.

Maria Caulfield Portrait Maria Caulfield
- Hansard - - - Excerpts

Absolutely. I take hon. and right hon. Members’ feedback about their frustration at how clearing the red tape in this process sometimes takes longer than the construction. My hon. Friend is right: this will be a novel way forward and could open the door for other trusts that are proactive in securing approval for their business cases in a more timely manner.

In addition to the energy centre, the Government are releasing funds to support the trust overall for the new hospital that we wish to build at Kettering, both for the development of the business case more widely and for some early critical works to prepare the site for main construction. By the end of this financial year—which is early next week—the scheme will have received over £5 million in development funding. That includes the release of over £1.9 million in fees to support with the design, planning permission and a business case for a new multi-storey car park. Further funding has also been released to support the development of business cases for the reprovision of accommodation, which will be needed during construction, the data centre and construction area and access roads, which will also be required.

I hope I have reassured my hon. Friend that we are doing extra work, in addition to the energy centre. We expect to receive the full business case and submissions over the course of this year. Again, we urge the trust to be as swift as it can with that, so that we can make some assessments and decisions as quickly as possible. Of course we will keep my hon. Friend updated as the scheme progresses and as further funding is released to the project, because we want to stay on track to complete the main construction of the new hospital by 2030.

In the short time I have, I want to update the House on the wider hospitals programme, because I know that hon. Members are often interested in the progress we are making. I am pleased to say that four of our new hospitals are now open to patients: the Northern Centre for Cancer Care in Newcastle, the Royal Liverpool Hospital, the Louisa Martindale, also known as the 3Ts hospital, in Brighton, and the Northgate and Ferndene Hospitals in Northumberland. A further four hospitals are expected to be open by the end of the next financial year: Salford Royal major trauma centre, the Dyson cancer centre in Bath, the national rehabilitation centre in Loughborough, and the Midland Metropolitan University Hospital. A further 18 hospitals are in construction or well under way towards completion. We also have other capital programmes, including over 100 rapid diagnostic centres that are open, 100 new surgical hubs that are either open or in construction, and 160 mental health crisis centres—all capital projects that will transform healthcare up and down England.

In conclusion, I again thank my hon. Friend the Member for Kettering. He has raised this issue, quite rightly, to hold our feet to the fire. He is fighting tooth and nail for his constituents to get the new hospital up and running by 2030. The energy centre will be the first major part of that construction. If the trust can get us the business case by June, the Hospitals Minister has committed to try to turn that round within a couple of weeks. That will be the start of the wider programme for the new hospital at Kettering. We will absolutely keep my hon. Friend updated, and the new hospital programme team will continue to do all it can to meet the challenges of delivering such a large infrastructure project, to ensure that staff and patients have world-class facilities in Kettering.

Question put and agreed to.