Today I am providing an update on our plans for the next stage of the Type 26 Global Combat Ship (T26 GCS) programme.

The 2015 Strategic Defence and Security Review (SDSR15) set out the Government’s clear commitment to build eight Anti-Submarine Type 26 Global Combat Ships, preceded by two additional offshore patrol vessels (OPVs), and to launch a concept study and then design and build a new class of lighter, flexible general purpose frigates.

Alongside work on the national shipbuilding strategy, we are working with industry to develop an optimised schedule for the Type 26 and OPV programmes. As part of this, we have agreed a contract with BAE Systems valued at £472 million to extend the T26 demonstration phase to June 2017.

This will enable us to mature further the detailed ship design, ahead of the start of manufacture, including investing in shore testing facilities, and extend our investment in the wider supply chain in parallel with the re-baselining work which is continuing.

The investment in shore-based testing facilities will test key parts of the ships’ power and propulsion system and the combat system to de-risk their future integration into the class.

Investment in the wider supply chain will cover further key equipment purchases for the first three Type 26 Global Combat Ships including the diesel generators, sonar domes, helicopter handling equipment, mission bay side doors and the stabiliser and steering gear systems, and demonstrates our ongoing commitment to invest in the UK’s ability to design, develop and deliver complex warships to meet the Royal Navy’s future capability needs.