Wednesday 15th July 2015

(9 years, 5 months ago)

Written Statements
Read Hansard Text Read Debate Ministerial Extracts
Philip Dunne Portrait The Minister for Defence Procurement (Mr Philip Dunne)
- Hansard - - - Excerpts

On 16 October 2014 I announced that the Ministry of Defence (MOD), Submarine Dismantling Project (SDP) public consultation process would take place between 14 November 2014 and 20 February 2015. Today I can announce, with the conclusion of that process, an initial report from the public consultation is being published online.

Five sites were shortlisted to house an interim store for intermediate level radioactive waste (ILW) removed from 27 nuclear submarines that have been, or will be, decommissioned. The interim store will have the capacity to hold all this ILW until it is transferred to a geological disposal facility (GDF) some time after 2040.

The public consultation sought views about the sites that had been shortlisted and how people felt about the site near them being chosen. The report draws together all the views and collates them under themes to provide a clear and accurate consensus of the opinions raised by site and subject.

This initial report contains only views from the public and no response from MOD as yet, this will come in a later report. It has been published today on the Government website at:

http://www.gov.uk/government/consultations/submarine-dismantling-project-site-for-the-interim-storage-of-intermediate-level-radioactive-waste

Moving forward, assessment continues, taking into account the public consultation findings and information that has been requested and gathered from the sites themselves. The five shortlisted sites are: AWE Aldermaston in Berkshire; AWE Burghfield in Berkshire; Capenhurst in Cheshire; Chapelcross in Dumfriesshire and Sellafield in Cumbria.

A final decision about which site will house the interim store will be made in 2016.

A copy of the report has been placed in the Library of the House.

[HCWS110]