Caledonian Modular

(asked on 29th November 2023) - View Source

Question to the Cabinet Office:

To ask His Majesty's Government which Government-funded construction projects had been awarded to Caledonian Modular prior to its collapse in March, including, for each project, the awarding department, the contract value, and the anticipated costs of remediation of defective work.


Answered by
Baroness Neville-Rolfe Portrait
Baroness Neville-Rolfe
Minister of State (Cabinet Office)
This question was answered on 13th December 2023

The Cabinet Office does not centrally hold commercial information on Government-funded construction projects. Individual departments manage and procure their own contracts. The Cabinet Office can confirm that no contracts with Caledonian Modular were held with the Cabinet Office prior to its collapse in March 2022.