High Speed 2 Railway Line

(asked on 27th January 2020) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what they estimate the total final cost of HS2 will be to the Exchequer.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 10th February 2020

To ensure transparency around the project, we have provided our latest cost and schedule estimates for HS2 to the National Audit Office who reported on the programme last week. These estimates depend, among other things, on the scope of what, if anything, the Government decides to build and which risks come to pass. In August 2019 the Government commissioned the independent Oakervee Review to provide advice on whether and how to proceed with HS2, including a rigorous examination of costs and schedule. The Government will make a decision on HS2 shortly.