High Speed 2 Railway Line

(asked on 14th May 2018) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government whether HS2 Ltd used an average per kilometre cost estimating model to calculate the total cost of earthworks along the HS2 Phase One and Phase Two routes.


Answered by
Baroness Sugg Portrait
Baroness Sugg
This question was answered on 23rd May 2018

The estimating methodology for the earthworks for C2 North Portal Chiltern Tunnels to Brackley section of the Phase One route and for the preferred Phase One aerial route at Wendover used by HS2 Ltd is the Civil Engineering Standard Method of Measurement (CESMM4).

In calculating the cost of earthworks along the Phase One and Phase Two route, HS2 Ltd created parameter cost models for all major civil assets including earthworks. The parameter cost models allowed HS2 Ltd to produce a consistent approach to the production of bottom up estimates for each type of asset incorporating cost drivers specific to HS2 Ltd.

These were then used by HS2 Ltd to provide detailed specific earthworks costs based upon specific quantities and cost drivers.