East Coast Railway Line: Repairs and Maintenance

(asked on 14th March 2017) - View Source

Question to the Department for Transport:

To ask Her Majesty’s Government, in the light of disruption to services on the East Coast mainline, what recent discussions they have held with Network Rail on its maintenance programme; and when the existing overhead electric wires will be replaced.


Answered by
 Portrait
Lord Ahmad of Wimbledon
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 27th March 2017

Whilst the maintenance and renewal of rail infrastructure, including the overhead electricity supply, is a matter for Network Rail overseen by the independent regulator, the Office of Rail and Road, we have regular discussions with Network Rail throughout the year regarding their performance. Future plans for renewal of overhead lines on this route will be set out in Network Rail’s Strategic Business Plan later this year.