West Coast Railway Line

(asked on 13th March 2017) - View Source

Question to the Department for Transport:

To ask Her Majesty’s Government, further to the Written Answer by Lord Ahmad of Wimbledon on 9 March (HL5562), whether the journey time of four hours and 17 minutes for the Pendolino to Glasgow allows for the same "minor line speed improvements on the northern West Coast Main Line" as for the four hour journey time quoted for Phase 1 non-tilt.


Answered by
 Portrait
Lord Ahmad of Wimbledon
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 23rd March 2017

The minor line speed improvements on the West Coast Main Line (WCML), mainly north of Preston, would increase the maximum permissible speed for non-tilting rolling stock to towards the maximum permissible speed for tilting rolling stock. These improvements would not therefore have any effect on the journey time of four hours and seventeen minutes for Pendolino services between London and Glasgow.