Question to the Department for Transport:

To ask Her Majesty’s Government what assessment they have made of the conclusion by the Office of Road and Rail that it will be possible, by 2021, to run 7.5 long distance trains per hour on the East Coast Main Line (ECML) in an operationally robust timetable, in the light of the eight interventions to improve the ECML identified in the 2011 Initial Industry Plan by Network Rail at a cost of £500 million, and the later announcement of funding of £240 million.


Answered by
 Portrait
Lord Ahmad of Wimbledon
Minister of State (Foreign, Commonwealth and Development Office)
This question was answered on 17th June 2016

The Government understands from work carried out by Network Rail that under the current plans for enhancement works on the route, 7.5 high speed paths would be available from 2021, although the detailed implications for the timetable and train performance have yet to be examined.