National Holocaust Memorial Centre and Learning Service: Planning Permission

(asked on 19th December 2019) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask Her Majesty's Government, following their decision to call in the planning application for a UK Holocaust Memorial, whether all the evidence submitted to Westminster City Council will be fully considered.


Answered by
Viscount Younger of Leckie Portrait
Viscount Younger of Leckie
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 7th January 2020

Following the decision to call in the planning application for the UK Holocaust Memorial and Learning Centre, the case will now proceed to a public inquiry overseen by an independent planning Inspector. The inquiry will consider evidence including that submitted to Westminster City Council, and is currently scheduled to begin on 27 May 2020.

Reticulating Splines