Crossrail 2 Line

(asked on 26th February 2020) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what is the latest cost estimate for Crossrail 2; and what proportion of its revenue is expected to come from passengers using HS2 at Euston.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 9th March 2020

Crossrail 2 is at an early stage of scheme development. The Government, Transport for London and Network Rail are currently working to refine the cost estimates for Crossrail 2, to reflect the findings of the Independent Affordability Review, ahead of a Spending Review. Cost estimates will become available once that work is completed and scheme development has reached an appropriate level of maturity. Revenue numbers at this level of detail are not available at this stage.

However, current analysis estimates that 50,000 passengers in total would board and alight Crossrail 2 services at Euston in the 2041 morning peak period (0700 to 1000). This represents approximately 10% of the total Crossrail 2 demand and around a fifth of Crossrail 2 passengers at Euston are expected to be using HS2 services.

These projections are regularly updated as part of ongoing updates to TfL’s forecasting models, and Crossrail 2’s business case analysis.