Public Footpaths: Coastal Areas

(asked on 25th February 2021) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask Her Majesty's Government what plans they have to publish the planned schedules for the completion of the England Coast Path.


This question was answered on 11th March 2021

Restrictions associated with the COVID-19 pandemic have resulted in some delays to the England Coast Path programme. It is still Defra’s intention, however, to have all stretches either open or with establishment works started by the end of 2021.

By the end of April, proposals for 99% of the path will have been published by Natural England. To date 1,483 miles (55%) of proposals for stretches of the England Coast Path have been approved by Secretary of State, 401 miles (15%) of which are already open to the public.

As further stretches are ready for opening, this will be published.