Railways: Capital Investment

(asked on 3rd February 2020) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government, further to the Written Answer by Baroness Vere of Norbiton on 16 January (HL122), whether projects funded by the “£500m to start reopening lines closed following the Beeching report, reconnecting smaller towns, regenerating local economies and improving accessibility to jobs, homes and education” will have to go through (1) the Rail Network Enhancement Pipeline, and (2) the Governance of Railway Investment Projects, systems.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 13th February 2020

We expect the Department for Transport’s Rail Network Enhancement Pipeline process and the Network Rail Governance of Railway Investment Projects process will be used to manage the development and delivery of re-opening schemes.