High Speed 2 Railway Line: Iron and Steel

(asked on 8th September 2020) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what proportion of steel used in phase one of the High Speed 2 project is British steel.


Answered by
Andrew Stephenson Portrait
Andrew Stephenson
Minister of State (Department of Health and Social Care)
This question was answered on 11th September 2020

The Government’s guidance on the procurement of steel was published in November 2015 and subsequently updated in December 2016. All major government projects are required to take cognisance of the Crown Commercial Service Procurement Policy Note 11/16: “Procuring Steel in Major Projects - Revised Guidance” (https://www.gov.uk/government/publications/procurement-policy-note-1116-procuring-steel-in-major-projects-revised-guidance ).

Whilst HS2 Ltd does not directly buy steel, it does apply a strategic and transparent approach to the sourcing of steel for the HS2 Programme through its Tier 1 contractors and their supply chains. HS2 Ltd ensures a fair procurement process which complies with UK procurement law and the Government policy on the procurement of steel.