The Government is currently investing £2.6 billion across the country to deliver more than 1,000 flood defence projects to better protect 300,000 homes by 2021. Since 2015, £24 million has been spent in Oxfordshire to reduce the risk of flooding. The Oxford Flood Alleviation Scheme is fully funded, and construction is due to begin after the replacement of the A423 Kennington Railway Bridge.

We are spending £5.62 million in Oxfordshire this year of which £2.3 million is on the Oxford Flood Alleviation Scheme which, when completed, will protect 1,200 homes. The rest of the money spent this year is towards other schemes, including looking at the early feasibility for schemes that could provide protection in the future if viable

In Abingdon, the previously proposed flood storage area to reduce flood risk is not being progressed due to the low number of properties that will have their flood risk reduced. Other options are currently being considered for the town.

Government funding is governed by the rules of the Partnership Funding Policy and the formula for allocating the Government’s contribution is weighted towards protecting people’s lives and homes.

The Environment Agency will continue to work with Oxfordshire County Council on solutions for flooding across the county.