Midland Main Railway Line: Repairs and Maintenance

(asked on 8th September 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, pursuant to the Answer of 7 July 2015 to Question 4429, on the Midland Main Line, for what works on which sites on the Midland Main Line for funding under the Passenger Journey Time Fund had been authorised; and what funding has been awarded to date to which of those works under the Passenger Journey Time Fund.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 13th September 2016

Network Rail has estimated between £29.5-£39.5m costs of the pause/un-pause of electrification.

Funding has been provisionally allocated from the Passenger Journey Improvement Time Fund (PJIF) to various schemes, including the Midland Main Line Programme. Subject to affordability and value for money, the allocated funds will be confirmed once schemes have completed the detailed design stage.

As part of the Hendy Review £90million was provisionally allocated to the MML from the PJIF fund for Control Period 5 of which:

Derby to Sheffield PJIF- £49.2m

Market Harborough PJIF - £27m (This denotes the PJIF element of funding for Market Harborough not the total cost of the scheme)

Leicester South PJIF - £8m

(2012/13 prices)