Planning Permission: Judicial Review

(asked on 5th May 2020) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask the Secretary of State for Housing, Communities and Local Government, what assessment his Department has made of the potential effect of reducing the time limit for bringing a judicial review in planning cases to six weeks, as implemented by the Government on 1 July 2013.


Answered by
Christopher Pincher Portrait
Christopher Pincher
This question was answered on 11th May 2020

Reducing the time limit for bringing a judicial review claim from 3 months to 6 weeks provides developers with more certainty to start construction of a project sooner after planning permission has been granted. We are not aware of any evidence to suggest that this measure has prejudiced access to justice for genuine claimants.