High Speed 2 Railway Line: Chesham and Amersham

(asked on 11th July 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, when he expects the timetable for construction of High Speed 2 Phase One in Chesham and Amersham constituency to be published.


Answered by
Robert Goodwill Portrait
Robert Goodwill
This question was answered on 13th July 2016

Finalising the construction timetable for works in this area will be the responsibility of the Main Works Contractor when they are appointed following Royal Assent. An indicative construction programme for Chesham and Amersham is set out in Volume 2 of the Environmental Statement (ES) - CFA reports 8-9. This indicates advanced works commencing in the first quarter of 2017, with civil engineering works commencing in the fourth quarter of 2017.