Railways

(asked on 24th May 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, with reference to the Answer of 21 July 2015, to Question 7665, what average number of pilings per shift was achieved by Network Rail's High Output Plant System train during (a) July to September 2015, (b) October to December 2015, (c) January to March 2016 and (d) April to May 2016.


Answered by
 Portrait
Claire Perry
This question was answered on 6th June 2016

The following information has been provided by Network Rail:

The average number of pilings per shift achieved by Network Rail’s High Output Plant System train during the following months was as follows:

a) July to September 2015 – 4.9 piles per shift.

b) October to December 2015 – 7.0 piles per shift.

c) January to March 2016 – 4.7 piles per shift.

d) April to May 2016 – 6.5 piles per shift.

Reticulating Splines