Question to the Ministry of Defence:
To ask the Secretary of State for Defence, pursuant to the Answer of 27 May 2022 to Question 5341 on Armed Forces: Housing, which of the high rise forces accommodation buildings has been replaced with a new build; and how much that cost his Department.
No high-rise Forces accommodation buildings have been replaced with a new build.
Nile Block at HMS Nelson is planned for demolition towards the end of 2025, to be replaced with a new build. The estimated costs of the re-development of Nile Block as well as several other buildings is included in one project, with total estimated project costs of £240 million.