High Speed 2 Railway Line

(asked on 11th April 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what estimate he has made of the (a) overall and (b) contingency for High Speed 2 (HS2) (i) Phase 1, (ii) Phase 2a, (iii) Phase 2b and (iv) rolling stock in 2015 prices; and what the overall expenditure has been on HS2 on the most recent date for which figures are available.


Answered by
Robert Goodwill Portrait
Robert Goodwill
This question was answered on 14th April 2016

The 2015 Spending Review reconfirmed the Government’s commitment to the programme providing a long-term funding envelope of £55.7bn in 2015 prices. A breakdown of this envelope with and without contingency has been provided below:

£'bn, 2015 Prices

Phase One

Phase 2a

Phase 2b

Rolling Stock

Total

Without Contingency

18.0

2.7

14.7

5.4

40.8

With Contingency

24.3

3.7

20.7

7

55.7

To date (2009/10 – 2015/16) the government has spent £1.5bn on the HS2 programme. Please note that actual expenditure data for 2015/16 is pre-audit.