High Speed 2 Railway Line: Finance

(asked on 12th July 2021) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, by how much was HS2 over budget in July 2019; and what information was shared with hon. Members on HS2 being over budget in 2019.


Answered by
Andrew Stephenson Portrait
Andrew Stephenson
Minister of State (Department of Health and Social Care)
This question was answered on 20th July 2021

In July 2019, the budget for the project remained £55.7bn (2015 prices). Cost and schedule pressures were known and work was continuing to identify options to ensure the overall affordability of the HS2 project – this is detailed in the National Audit Office’s January 2020 HS2 progress report. The independent Oakervee review was formally commissioned in August 2019 to enable government to make properly-informed decisions on the future of the project, including the estimated cost and schedule position. A revised funding envelope was agreed in April 2020 with 6 monthly updates now provided to Parliament to allow full scrutiny of the project.

Reticulating Splines