Hinkley Point C Power Station

(asked on 8th March 2016) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Energy and Climate Change, with reference to the Annex on a Comprehensive Franco-British Partnership on Civil Nuclear Energy, Franco-British Summit, on 3 March 2016, what the basis is for the statement that major progress has been made in recent months with a view to confirming the project to build two EPR reactors on the Hinkley Point site.


Answered by
Andrea Leadsom Portrait
Andrea Leadsom
Parliamentary Under-Secretary (Department of Health and Social Care)
This question was answered on 11th March 2016

The terms of the contractual documentation relating to Hinkley Point C (Contract for Difference, Secretary of State Investors Agreement, Funded Decommissioning Programme (FDP) and related Waste Transfer contracts) between the Government and EDF are in final form.

EDF and CGN have confirmed major investment in HPC and are working to rapidly conclude the detailed investment documentation.

The Final Investment Decision is a matter for EDF and we understand they will make this shortly.

In January we gave planning consent for the National Grid connection to Hinkley Point C.