RAF Northolt: Repairs and Maintenance

(asked on 14th May 2019) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, pursuant to the Answer of 12 March 2019 to Question 228557 on RAF Northolt: Repairs and Maintenance, what progress he has made on (a) the runway and (b) associated infrastructure construction works; what estimate his Department has made of the cost of those works; and if he make a statement.


Answered by
Tobias Ellwood Portrait
Tobias Ellwood
This question was answered on 20th May 2019

The runway was closed as planned on 15 April 2019 to fixed wing aircraft. Rotary wing operations have continued, while fixed wing aircraft are now operating from RAF Benson.

Construction works have commenced to remove the existing runway surface and arrestor beds. This will be followed by preparatory works for resurfacing the runway, installation of new arrestor beds and new approach lighting. Works will continue through summer to be completed in late October 2019.

The estimated capital cost of the project is £23 million inclusive of VAT. The works will assure military flying operations in support of UK Defence and the wider Government at RAF Northolt for the next 10 - 15 years.