Infrastructure: Finance

(asked on 23rd June 2021) - View Source

Question to the HM Treasury:

To ask the Chancellor of the Exchequer, what the timetable is for publication of the Infrastructure and Projects Authority's next iteration of the National Infrastructure and Construction Procurement Pipeline, last published on 16 June 2020.


Answered by
Jesse Norman Portrait
Jesse Norman
This question was answered on 28th June 2021

The Infrastructure and Projects Authority publishes a National Infrastructure and Construction Pipeline annually, subject to Ministerial approval. The last Pipeline was published in response to COVID-19 and set out planned procurements with an estimated contract value of up to £37bn across the 2020/21 financial year. The next iteration of the National Infrastructure and Construction Pipeline will be published later this year and will set out future investment alongside planned procurements.