Railways: Electrification

(asked on 5th January 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, pursuant to the Answer of 5 January 2016 to Question 20640, how many miles of track will be electrified by the end of Control Period 5 under the timetable for project delivery contained in Sir Peter Hendy's review of the rail upgrade programme.


Answered by
 Portrait
Claire Perry
This question was answered on 11th January 2016

Pursuant to the Answer of 5 January 2016 to Question 20640, we remain committed to our modernisation programme of over 850 miles of electrification.


Sir Peter Hendy’s review of the rail upgrade programme details that the vast majority of programmes and projects will go ahead for delivery by 2019 (the end of Control Period 5).


However, some schemes are more immature in their development and, whilst schemes in this category will have significant delivery within Control Period 5, these schemes will span more than one control period.


Electrification provides long-term efficiencies for the railways, but it is just one element of a wider set of railway upgrades to provide better journeys for passengers and freight users.