Dungeness B Power Station

(asked on 4th June 2014) - View Source

Question

To ask the Secretary of State for Energy and Climate Change, what information has been provided to his Department by (a) EDF Energy and (b) the Office for Nuclear Regulation on the application by EDF Energy to extend the operating life of the Dungeness B reactor.


Answered by
Michael Fallon Portrait
Michael Fallon
This question was answered on 11th June 2014

In December 2013, the Nuclear Decommissioning Authority (NDA) received a notification from EDF Energy of the intention to extend the planned operating life of Dungeness B AGR power station (as required under the Nuclear Liabilities Funding Agreement). Information relating to this process was shared with the Department. The decision on whether in practice to extend the life of the plant will be a commercial matter for EDF Energy. This is subject to the relevant safety and security regulations.