Fracking: Lancashire

(asked on 14th November 2018) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, if he will publish any reports provided by Cuadrilla Bowland Ltd to the Oil and Gas Authority on the four seismic events of greater than the red light 0.5ML threshold that occurred at the Preston New Road shale gas site between 26 October 2018 and 4 November 2018.


Answered by
 Portrait
Claire Perry
This question was answered on 3rd December 2018

The Oil and Gas Authority (OGA) monitors seismicity as part of their regulatory duties at shale gas sites. They review all information submitted to them by Cuadrilla and have assured the Government that events at Preston New Road are conforming to the pre-agreed Hydraulic Fracture Plan.

Information about the seismic events is displayed real-time on the British Geological Survey (BGS) site and Cuadrilla regularly update information on traffic light events on their web-site.

Within 30 days of completion of operations the operator must submit a Hydraulic Fracturing Operations Report to the OGA. The OGA will publish these reports six months after receipt.