Question to the Department for Transport:
To ask the Secretary of State for Transport, pursuant to the Answer of 21 September 2015 to Question 10029, which schemes referred to in that Answer have been paused by Network Rail.
The Secretary of State announced on 25 June 2015 the pause of work on Midland Main Line electrification and TransPennine electrification.
On 30 September 2015 he announced that work on these schemes would resume.
Whilst Sir Peter Hendy completes his review of Network Rail’s Enhancements programme, the efficient and cost effective delivery of other projects is a matter for Network Rail to manage.